Springdale Combined Cycle Power Plant is a 556MW gas fired power project. It is located in Pennsylvania, the US. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in July 2003.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 556 | 556 | – | Active | Pennsylvania, the US |
---|
Description
The project is currently owned by Aspen Generating with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Distillate Fuel Oil. The fuel is procured from Dominion.
The project generated 3,977,201MWh of electricity.
The Gas fired project consists of 1 steam turbine with 188MW nameplate capacity.
Development Status
The project got commissioned in July 2003.
Contractors Involved
Siemens was selected as the turbine supplier for the Gas fired project. The company provided 2 units of SGT6-5000F gas turbines, each with 184MW nameplate capacity.
Siemens Heat Transfer Technology supplied steam boiler for the project.
IHI Power Services is the O&M contractor for thermal power project. The operation and maintenance contract commenced from 2017, for a period of 5 years.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.