T Plus-Sorochinsk Solar PV Park is a 60MW solar PV power project. It is located in Orenburg, Russia. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in November 2018.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Solar PV 60 60 Active Orenburg, Russia T Plus Group

Description

The project is developed and owned by T Plus Group.

T Plus-Sorochinsk Solar PV Park is a ground-mounted solar project which is spread over an area of 123.3 hectares.

The project cost is $142.707m.

Development Status

The project got commissioned in November 2018.

Contractors Involved

Hevel Group was selected as the supplier of the PV modules for the project. The company installed 202,075 modules at the site.

The project is utilising trackers supplied by Agrisovgaz.

About T Plus Group

T Plus Group (T Plus) is an energy utility company engaged in the generation, transmission, and distribution of electric power and heat supply. Its business operations include production of heat and electric energy; retail sale of electricity; transmission and sale of thermal energy; trading of fuel and wholesale electricity; project development of generation plants; construction and rehabilitation of modern and efficient generating capacities; and energy saving and energy efficiency solutions. T Plus operates a network of thermal, hydro and solar power plants, as well as power stations. It provides services to commercial, industrial and government sectors. T Plus is headquartered in Krasnogorsk, Moscow Oblast, Russia.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.