Tres Hermanas is a 97.15MW onshore wind power project. It is located in Ica, Peru. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in March 2016.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Onshore 97.15 97.15 Active Ica, Peru Cobra Instalaciones y Servicios

Description

The project is developed and owned by Cobra Instalaciones y Servicios. The company has a stake of 100%.

The project generates 415,760MWh electricity and supplies enough clean energy to power 90,000 households, offsetting 428,000t of carbon dioxide emissions (CO2) a year. The project cost is $185.7m.

Development Status

The project is currently active. The project got commissioned in March 2016.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Power Purchase Agreement

The power generated from the project is sold to Sistema Electrico Interconectado Nacional under a power purchase agreement. The power is sold at the rate of $0.069kWh for a period of 20 years. The contracted capacity is 97.15MW.

Contractors Involved

Cobra Instalaciones y Servicios was selected to render EPC services for the wind power project.

Tres Hermanas (Tres Hermanas I) is equipped with Siemens Gamesa Renewable Energy SWT-3.0-108 turbines. The phase consists of 25 turbines with 3.15MW nameplate capacity.

Tres Hermanas (Tres Hermanas II) is equipped with Siemens Gamesa Renewable Energy SWT-2.3-108 turbines. The phase consists of 8 turbines with 2.3MW nameplate capacity.

Siemens Gamesa Renewable Energy is the O&M contractor for the wind power project for a period of 6 years.

CS Wind has supplied towers for the wind power project.

About Cobra Instalaciones y Servicios

Grupo Cobra is a Spain based Company that delivers engineering, operations, installation and maintenance services.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.