U Thai Power Project is a 1,600MW gas fired power project. It is located in Phra Nakhon Si Ayutthaya, Thailand. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in June 2015.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 1,600 | 1,600 | – | Active | Phra Nakhon Si Ayutthaya, Thailand | Gulf JP UT |
---|
Description
The project was developed by Gulf JP UT. Electric Power Development and Gulf Energy Development are currently owning the project having ownership stake of 60% and 40% respectively.
It is a combined cycle gas turbine (ccgt) power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Diesel.
Development Status
The project got commissioned in June 2015.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataPower Purchase Agreement
The power generated from the project is sold to Electricity Generating Authority of Thailand under a power purchase agreement for a period of 25 years. The contracted capacity is 1,600MW.
Contractors Involved
Mitsubishi Power was selected to render EPC services for the gas fired power project.
Mitsubishi Power was selected as the turbine supplier for the Gas fired project. The Gas fired project consists of 2 steam turbines.
Mitsubishi Power was selected as the turbine supplier for the Gas fired project. The company provided 4 units of M701F4 – 50Hz gas turbines.
Mitsubishi Power supplied electric generator for the project.
Nooter/Eriksen supplied steam boiler for the project.
Mitsubishi Power is the O&M contractor for thermal power project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.