UTE GNA I Power Plant is a 1,338MW gas fired power project. It is located in Rio de Janeiro, Brazil. The project is currently active. It has been developed in single phase. The project construction commenced in 2019 and subsequently entered into commercial operation in September 2021.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 1,338 | 1,338 | – | Active | Rio de Janeiro, Brazil | UTE GNA I Geracao de Energia |
---|
Description
The project was developed by UTE GNA I Geracao de Energia. BP, Prumo Logistica and Siemens Energy are currently owning the project.
It is a combined cycle gas turbine (ccgt) power plant. The fuel is procured from FSRU BW Magna.
The project cost is $1,163.47m.
Development Status
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataThe project construction commenced in 2019 and subsequently entered into commercial operation in September 2021.
Contractors Involved
Andrade Gutierrez and Siemens were selected to render EPC services for the gas fired power project.
Siemens Energy was selected as the turbine supplier for the Gas fired project. The company provided 3 units of SGT6-8000H gas turbines.
Siemens Energy was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of SST6-5000 steam turbine.
Siemens Energy supplied electric generator for the project.
Siemens Energy supplied steam boiler for the project.
Siemens is the O&M contractor for thermal power project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.