Victorias Biomass Fired Power Plant is a 74MW biopower project. It is located in Negros Oriental, Philippines. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in June 2012.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Biopower | 74 | 74 | – | Active | Negros Oriental, Philippines |
---|
Description
The project is currently owned by Victorias Milling.
The process of combustion has been adopted in this combined heat and power (CHP) project to release the stored energy from the feed. Bagasse which is a kind of agricultural by-product is used as a feedstock to power the project.
Victorias Biomass Fired Power Plant (Victorias Biomass Fired Power Plant Phase II) consists of 3 turbines.
Development Status
The project got commissioned in June 2012.
Contractors Involved
Victorias Biomass Fired Power Plant (Victorias Biomass Fired Power Plant Phase I) is equipped with Shin Nippon Machinery turbine. The phase consists of 1 turbine with 8MW nameplate capacity.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.