Wako Kungo Substation is a 400/220kV substation located in Wako kungo, Cuanza Sul, Angola. The construction works on Wako Kungo Substation began in 2019. The project was commissioned in 2021.

Description

The Wako Kungo Substation project is an upgrade substation being operated by Rede Nacional de Transporte de Electricidade.

The designed voltage level of the project is 400/220kV, while the operating voltage level is 400/220kV. The step-in voltage of the substation is 400kV and the step-out voltage is 220kV. The substation capacity is 450MVA.

Wako Kungo Substation has received approval from Instituto Regulador dos Servicos de Electricidade e de Agua to undertake the works on the project. Approximately $40.5m was financed by the authorities for the construction works of the project.

Methodology

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

All publicly-announced T&D Line & Substation projects included in this analysis are drawn from GlobalData’s Power IC. The information regarding the projects is sourced through secondary information sources such as country specific utility players, company news and reports, statistical organisations, regulatory body, government planning reports and their publications and is further validated through primary from various stakeholders such as power utility companies, consultants, energy associations of respective countries, government bodies and professionals from leading players in the power sector.