Wyoming – Colorado Intertie Line is a 345kV overhead line with a length of 289.68km from Wyoming, Wyoming, US, to Colorado, Colorado, US.

The project, which is currently in the planning stage, is expected to be commissioned in 2021.

Description

Wyoming – Colorado Intertie Line is an overhead line that will be operated by LS Power Associates. The line will carry alternating current (AC) through double circuit cable.

Approximately $300m was financed by the authorities to undertake the construction works of the project.

Wyoming – Colorado Intertie Line project development status

GlobalData Strategic Intelligence

US Tariffs are shifting - will you react or anticipate?

Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.

By GlobalData

The construction works on the Wyoming – Colorado Intertie Line project commissioning is expected in 2021.

Methodology

All publicly-announced T&D Line & Substation projects included in this analysis are drawn from GlobalData’s Power IC. The information regarding the projects is sourced through secondary information sources such as country specific utility players, company news and reports, statistical organisations, regulatory body, government planning reports and their publications and is further validated through primary from various stakeholders such as power utility companies, consultants, energy associations of respective countries, government bodies and professionals from leading players in the power sector.