Zhejiang Xiaoshan Combined Cycle Power Plant is an 806MW gas fired power project. It is located in Zhejiang, China. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in August 2007.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 806 | 806 | – | Active | Zhejiang, China |
---|
Description
The project is currently owned by Zhejiang Southeast Electric Power with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The fuel is procured from Zhejiang Provincial Energy Group Company Ltd..
Development Status
The project got commissioned in August 2007.

US Tariffs are shifting - will you react or anticipate?
Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.
By GlobalDataPower Purchase Agreement
The power generated from the project is sold to East China Grid under a power purchase agreement.
Contractors Involved
Siemens was selected as the turbine supplier for the Gas fired project. The company supplied SGT-4000F model gas turbines for the project.
Siemens supplied electric generator for the project.
Hangzhou Boiler Group supplied steam boiler for the project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.