OMERS and Transmission Developers Infrastructure – Canada (TDI) have entered into a partnership to take part in the Independent Electricity System Operator’s (IESO) upcoming procurement process for the Toronto Third Line (TTL) transmission project.
This initiative aims to reinforce electricity supply to Toronto and its surrounding areas through a 65km underwater high-voltage direct current (HVDC) transmission line connecting Bowmanville and downtown Toronto via Lake Ontario.
Discover B2B Marketing That Performs
Combine business intelligence and editorial excellence to reach engaged professionals across 36 leading media platforms.
The TTL project, which has received approval from Ontario’s Minister of Energy, is expected to provide up to 900MW of electricity to the city, said to be sufficient to power around 900,000 homes.
The IESO procurement process for the project is currently scheduled to commence in 2027. The planned transmission line will deliver renewable energy directly to Toronto’s downtown core using an underwater HVDC cable, with the aim of ensuring grid reliability and supporting the growing demand for electricity in Canada’s largest city.
According to the companies, Ontario’s electricity demand in Toronto is projected to double by 2050. The TTL will become the province’s first underwater HVDC line and its first major domestic HVDC transmission project.
The collaboration brings together OMERS’ experience in infrastructure investment and management with TDI’s expertise in constructing buried HVDC cables.
The TDI team, which previously completed the 545km Champlain Hudson Power Express (CHPE) in the US, brings relevant experience, particularly with complex underground and underwater transmission lines.
OMERS Infrastructure and Private Equity executive vice-president and global head Michael Hill said: “The Toronto Third Line represents an opportunity to invest in essential infrastructure designed to support Toronto’s growing electricity demand and long-term system reliability that will serve Ontario communities for generations while delivering long-term value for OMERS members.
“Together with TDI’s proven experience developing and delivering complex HVDC transmission projects, we bring the investment discipline, technical expertise and long-term commitment to compete for this important project for Ontario.”
OMERS and TDI have said they will draw on previous projects such as the East-West Tie in Northern Ontario and the CHPE project to inform their approach to the TTL.
The partners have highlighted principles including safety, stakeholder engagement, environmental management, and long-term value for electricity users.
In addition, OMERS has noted support from the Toronto-based Kilmer Group, an investment platform with experience in the development and operation of Canadian infrastructure assets.