McDermott begins construction of TenneT’s BorWin6 HVDC project

Expected to be commissioned in 2027, BorWin6 is TenneT’s fifth project to be implemented off the coast of Borkum, Germany.

Surya Akella July 06 2023

McDermott, an engineering services provider for the energy industry, has begun construction work on TenneT’s 980MW high-voltage direct current (HVDC) transmission project, BorWin6, in the German North Sea.

The construction began with a steel-cutting ceremony at McDermott’s Jebel Ali fabrication yard in Dubai in the United Arab Emirates.

McDermott secured the contract as part of a consortium that also includes the Global Energy Interconnection Research Institute and C-EPRI Electric Power Engineering.

It will offer engineering, procurement, construction, installation and commissioning (EPCIC) services for the HVDC offshore converter platform.

McDermott onshore senior vice-president Vaseem Khan stated: “We have successfully delivered engineering from our HVDC centre of excellence in the Hague, and are on track to begin construction for this important offshore grid connection project.

“During this next phase, we will leverage our strategically located fabrication yards to drive execution excellence while maintaining our industry-leading safety record.”

Fabrication works will be conducted at the company’s yards in Dubai and in Batam, Indonesia.

Expected to be commissioned in 2027, BorWin6 is TenneT’s fifth project to be implemented off the coast of Borkum, Germany.

The offshore grid connection system has a total length of about 235km and uses extra-high-voltage direct current transmission technology.

It will be used to connect directly to wind turbines through 66kV cables.

The electricity generated at sea can be fed into TenneT’s converter platform where the alternating current (AC) is converted into direct current (DC) at the converter station.

The DC electricity will be transported to shore at Büsum via 190km submarine cables, then transmitted along 45km underground cables to the planned onshore converter station in Büttel to be converted into AC and fed into the extra-high-voltage grid.

Uncover your next opportunity with expert reports

Steer your business strategy with key data and insights from our latest market research reports and company profiles. Not ready to buy? Start small by downloading a sample report first.

Newsletters by sectors

close

Sign up to the newsletter: In Brief

Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Thank you for subscribing

View all newsletters from across the GlobalData Media network.

close