UK’s National Grid to fast-track 20GW clean energy connections

A total of 19 battery storage projects will be offered grid connections four years ahead of their existing arrangements.

Surya Akella November 07 2023

The UK’s National Grid is speeding up the connection of up to 20GW of clean energy projects to its electricity transmission and distribution networks across England and Wales.

The new policy is part of the electricity system operator’s (ESO) connections reform initiative to increase transmission capacity.

It is being implemented by the National Grid Electricity Transmission (NGET), which designs and builds transmission infrastructure to connect with the projects.

The operator stated that 19 battery energy storage projects totalling 10GW will be expedited for its transmission network.

The projects will be offered connections four years ahead of their existing agreements, using a new approach that eliminates the need for non-essential engineering works before connections are made.

A further 10GW of unlocked capacity in the Midlands, South West of England and South Wales distribution networks will see grid connection dates of some low-carbon projects fast-tracked by up to five years.

The ESO is in contact with more than 200 projects that are interested in accelerating their distribution connection dates.

Of these, 16 projects are interested in connecting within the 12 months to November 2024 while 180 intend to connect within two to five years.

The plan to speed up 20GW of capacity comes after months of engagement with the industry, regulator Ofgem and the UK Government to find solutions that hasten clean energy connections.

NGET president Alice Delahunty stated: “We are committed to speeding up connections and creating a 'fit for the future' process for plugging projects into the grid.

“Bringing these battery projects forward is one of a range of actions that our electricity transmission business is delivering alongside the system operator and wider industry to unlock clean energy capacity in England and Wales.

“We are really encouraged by the recognition these early joint steps by our industry are receiving. They are paving the way for the more fundamental connections reform that we are collectively working with government and the regulator to deliver to keep Britain on track for a secure, affordable and net-zero energy system.”

A further 10GW of renewable projects, in particular battery projects and hybrid projects in which batteries are co-located with wind or solar, are expected to provide faster connections in 2024.

Nuclear Power dynamics in China

The Chinese government holds nuclear power to be a key instrument in achieving clean energy. During their 13th Five-Year Plan period from 2016 to 2020, China built 20 new nuclear power plants with a total capacity of 23.4 GW. In the current 14th Five Year Plan period the government has set targets to achieve 70GW of nuclear power capacity by 2025. The government has no plans to phase out or phase down nuclear power plants and there are over 17 nuclear power projects under construction.

Newsletters by sectors

close

Sign up to the newsletter: In Brief

Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Thank you for subscribing

View all newsletters from across the GlobalData Media network.

close