Herdecke 400MW CCGT Gas-Fired Power Plant, Grenada

Announcement of contract

May 2005

Start of construction

September 2005

Start of testing

May 2007

Start of operation

October 2007

Output

400MW

Plant type

CCGT

Location

Herdecke, near Dortmund (North Rhine-Westphalia), Germany

Estimated investment

€200m

Plant owner

Statkraft and Mark-E each own 50%

Project Development and Implementation

Mark-E

Operator

Herdecke (KGH)

Principal Contractor

Siemens Power Generation

Gas supply

Wingas GmbH

Gas supply

Wingas GmbH

Gas supply

Wingas GmbH

Gas Turbines

270MW gas turbine with HRSG and 147MW steam turbine

Efficiency

Above 57.5%

Fuel

Natural gas-fired
Expand

Free download worth over $5000
Download our 2019 Technology, Media and Telecoms Predictions Report

Worth up to $5,850

In this report, we look at the 30 big tech themes for 2019, identifying winners and losers for each theme. This report will impact all industries helping:

  • CEOs/Senior Staff: in all industries understand the disruptive threats to their competitive landscape
  • Investors: Helps fund managers focus their time on the most interesting investment opportunities in global TM
Close
Close
Close

© Copyright 2019 Verdict Media Limited.

Go Top