Power Technology | Energy News and Market Analysis is using cookies

We use them to give you the best experience. If you continue using our website, we'll assume that you are happy to receive all cookies on this website.

ContinueLearn More X
X

Herdecke 400MW CCGT Gas-Fired Power Plant, Grenada

Announcement of contract

May 2005

Start of construction

September 2005

Start of testing

May 2007

Start of operation

October 2007

Output

400MW

Plant type

CCGT

Location

Herdecke, near Dortmund (North Rhine-Westphalia), Germany

Estimated investment

€200m

Plant owner

Statkraft and Mark-E each own 50%

Project Development and Implementation

Mark-E

Operator

Herdecke (KGH)

Principal Contractor

Siemens Power Generation

Gas supply

Wingas GmbH

Gas supply

Wingas GmbH

Gas supply

Wingas GmbH

Gas Turbines

270MW gas turbine with HRSG and 147MW steam turbine

Efficiency

Above 57.5%

Fuel

Natural gas-fired
Expand

Go Top