View all newsletters
Receive our newsletter - data, insights and analysis delivered to you
  1. Project
14 May 2014

Meerwind Süd│Ost Wind Project, North Sea

The 288MW Meerwind Süd │Ost offshore wind project, in the German North Sea, comprises two of the world's biggest offshore wind farms, Meerwind Süd and Meerwind Ost.
The 288MW Meerwind Süd │Ost offshore wind farm is located in the German North Sea. Image courtesy of WindMw.
The project generates 288MW of power using 80 Siemens 3.6MW wind turbines. Image courtesy of WindMW.
Seajacks placed the turbine blades using Zaratan vessel.
Alstom provided the offshore substation for the project. Alstom provided the offshore substation for the project.
HelWin1 North Sea platform will convert the AC power generated at the wind farm into DC power. Image courtesy of Siemens AG, Munich/Berlin.

Meerwind Sud

Free Report
img

Wind Power Market seeing increased risk and disruption

The wind power market has grown at a CAGR of 14% between 2010 and 2021 to reach 830 GW by end of 2021. This has largely been possible due to favourable government policies that have provided incentives to the sector. This has led to an increase in the share of wind in the capacity mix, going from a miniscule 4% in 2010 to 10% in 2021. This is further set to rise to 15% by 2030. However, the recent commodity price increase has hit the sector hard, increasing risks for wind turbine manufacturers and project developers, and the Russia-Ukraine crisis has caused further price increase and supply chain disruption. In light of this, GlobalData has identified which countries are expected to add the majority of wind power capacity out to 2030. Get ahead and download this whitepaper for more details on the current state of the Wind Power Market.
by GlobalData
Enter your details here to receive your free Report.

The 288MW Meerwind Süd │Ost offshore wind project, in the German North Sea, comprises two of the world’s biggest offshore wind farms, Meerwind Süd and Meerwind Ost.

Construction began in August 2012 and the final turbine was installed in April. The project is expected to produce clean energy that will power approximately 360,000 German houses, while offsetting approximately one million tonnes of carbon emissions every year.

The development phase created approximately 2,000 construction jobs and is expected to create 80 full-time operational jobs.

WindMW, a joint-venture of Blackstone and Windland Energieerzeugungs, developed the project with an investment of €1.2bn ($1.64bn), making it Germany’s first offshore wind project to be wholly financed by private investors.

Meerwind Süd│Ost wind project design

The offshore power project is located 23km north of the Helgoland Island in the North Sea, and extends over 42km. It features 80 Siemens SWT-3.6-120 wind turbines with a capacity of 3.6MW each. Each turbine, with a rotor diameter of 120m, stands 149m tall and has an elevation of 89m.

"The project is expected to produce clean energy that will power approximately 360,000 German houses."

The turbines are installed at water depths ranging from 22m to 26m. More than 110km of inter-array subsea power cables and associated terminations, supplied by JDR, are used to link the turbine generators to the offshore substation. The cables, equipped with hang-off termination technology, help in improving the speed and safety of installation, while minimising the vessel on-station time.

More than 85,000t of steel, 48,000m² of offshore coating and 4,200 pieces of shell plate were used to manufacture the monopiles for the project. Ambau manufactured the monopiles and transition pieces at its Cuxhaven and Bremen manufacturing units.

The wind farm is operated and maintained from the new service stations at Heligoland.

Construction of the wind farms

The first phase of construction, involving the ramming of 80 monopiles, was completed in April 2013. The first foundations were transported to the offshore site in September 2012, and the turbine blades were lifted and placed by Seajack’s Zaratan vessel.

Power transmission to the grid

The alternating current (AC) power generated by the wind turbines is transmitted to the offshore substation and further transferred to the HelWin1 offshore platform, developed by Siemens, for conversion into DC current, before transmission to the onshore substation.

Approximately 45km of land cable route was used to connect the offshore platform with the onshore substation at Büttel. The DC power is converted back into AC power at Büttel and is fed into the national grid.

Financing of the project

Financing for the project was provided by a consortium of seven commercial banks, along with EKF, the export credit agency of Denmark, and KfW-Bankengruppe. The consortium consisted of Commerzbank, KfW IPEX-Bank, Bank of Tokyo-Mitsubishi, Dexia, Lloyds Banking Group, Santander and Siemens Bank.

Contractors involved with the German offshore wind project

The contract for the supply, installation and commissioning of the wind turbine generators was awarded to Siemens. This included the service and maintenance of turbines for a period of five years.

A consortium of Alstom Grid and WeserWind was contracted for delivering the offshore substation. Alstom Grid was responsible for the design, manufacturing and commissioning of the substation, along with the design and supply of electrical components, while WeserWind designed and manufactured the platform’s steel structure, including a helicopter landing deck and the platform jacket.

"Approximately 45km of land cable route was used to connect the offshore platform with the onshore substation at Büttel."

Ambau signed a deal to construct the monopile sets, while Seajacks was awarded the contract for installing the monopiles, scour and the wind turbine generators. Seaway Heavy Lifting won the contract to install the offshore substation.

The construction of the seabed at the farm site went to Boskalis, while VSMC was awarded the contract to install the power cables.

Fichtner provided consultancy services for the design of scour protection, technical and economic optimisation, and other technical and contractual services. Knabe Enders Duhrkop (KED) was awarded the contract for designing the scour protection for the monopile foundations, and estimations of scour depths at jacket foundations.

K2 Management acted as the owner’s engineer and TenneT TSO was awarded the contract to operate the transmission system.

NRI Energy Technology

Topics in this article:
NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU

Thank you for subscribing to Power Technology