Projects

Mojave Solar Thermal Power Facility, San Bernardino County, California

Mojave Solar Project (MSP) is a 250MW solar thermal power facility located in San Bernardino County, California, US.

Plant Type
Solar thermal
Location
San Bernardino County, California
Capacity
250MW
Estimated Investment
$1.6bn
Area
1,765 acres
Owner
Mojave Solar
Developer
Abengoa Solar
Construction Started
2011
Completion
2014

The Mojave solar thermal facility

Mojave Solar Project (MSP) is a 250MW solar thermal power facility located in San Bernardino County, California, US. The site is located 100 miles (160.9km) away from Los Angeles.

Abengoa Solar, through its subsidiary Mojave Solar, built, operates and maintains the plant. Construction of the project started in 2011 with commercial operations following in December 2014.

The facility generates enough power to serve 54,000 households and reduces 355,000t of CO2 emissions per year. It is designed for an operational life of 30 years and will produce 617,000MWh of power per year.

Pacific Gas & Electric (PG&E) will purchase the power generated from the solar thermal facility as part of a 25-year power purchase agreement (PPA) with Abengoa Solar.

The project will benefit the state economically and environmentally, supporting the state’s goal for clean energy. The estimated investment was $1.6bn.

Location of Mojave Solar facility

The Mojave solar thermal facility is built across an area of 1,765 acres (714.2ha) of land, located approximately nine miles (14.5km) away from the Hinkley community, near Harper Dry Lake.

The site is divided into two parts (or power islands) of 125MW each, with an interconnection substation in the middle.

Located in the north-west, the Alpha site contains part of the solar assembly over 884 acres. The Beta site, located in the south-east, hosts the remaining solar mirrors in 800 acres.

Power generated from the two sites is transmitted to the central interconnecting substation.

“Abengoa Solar, through its subsidiary Mojave Solar, built, operates and maintains the plant.”

Technology at the solar thermal power facility

The cutting-edge concentrating solar technology generates electricity by reflecting solar rays from the array of parabolic trough mirror assemblies onto a heat collection element.

“The site is divided into two parts (or power islands) of 125MW each, with an interconnection substation in the middle.”

Parabolic mirrors are installed in parallel rows on the trough assemblies, in a north-south alignment. The mirrors store the solar radiation on a receiver tube.

The heat collection element receives the heat from the mirror assembly and uses it to raise the temperature of a fluid that is passed to solar steam generator heat exchangers. The steam emanating from these exchangers is fed to two steam turbine generators that produce electricity.

A wet cooling tower has also been built. It consists of a shell and tube heat exchanger that uses ground water to cool down the exhaust steam from the turbines to condensate. It uses approximately 2.65 million cubic metres of ground water a year.

In addition, administration and mirror assembly buildings have been constructed at the site. The assembling building is now being used as warehouse. In total, the project involved 185,000 square feet of new buildings.

SCE grid network connection

Electricity generated by the plant is fed to the grid network of Southern California Edison (SCE). A new substation has been constructed at Lockhart to interconnect the MSP with the Coolwater-Kramer 220kV transmission line owned by SCE and and other substations in the region.

The Lockhart substation is located within the MSP site, spread across ten acres of land.

The interconnection with various substations of the region required approximately 100 miles (160.9km) of new fibre optical wires. These fall outside of the project area.

Mojave Solar contractors

“Electricity generated by the plant is fed to the grid network of Southern California Edison (SCE).”

Abentey, a joint venture between Teyma International and Abener Energía, was awarded the engineering, procurement and construction (EPC) contract of the project.

Aspen provided the environmental impact assessment for the project, assisting California Energy Commission with the project approval process.

Ram Jack Solar Solutions was contracted for the construction of foundations for the solar structures.
The US Department of Energy (DOE) approved a $1.2bn loan guarantee, which was issued through the loan programme office.


Related content


Desert Sunlight Solar Farm, Riverside County, California, US

Desert Sunlight Solar Farm is a 550MW photovoltaic (PV) solar power project being built across 4,100 acres land in the Chuckwalla Valley.

Topaz Solar Farm, California, United States of America

Topaz Solar Farm is a 550MW photovoltaic (PV) solar power project being built in the east San Luis Obispo County, California.

Victorville Solar Power Generating Station, California, United States of America

Southern California Edison (SCE) and Stirling Energy Systems(SES) are building a huge 1,800ha (4,500ac) solar power generating station in Southern California.

Alta Wind Energy Center (AWEC), California, US

Alta Wind Energy Center (AWEC), also known as Mojave Wind Farm, is the second largest onshore wind energy project in the world.


Related Projects

Datan Power Plant Expansion, Taoyuan

Taiwan’s largest natural gas-fired combined-cycle power plant, Datan (also known as Tatan or Dah-Tarn power plant), is located in Taoyuan…