Projects

Rampion Offshore Wind Project, English Channel

Rampion Offshore Wind Project is being developed in the English Channel, 13km off the coast of Sussex in south-east England. The project is being developed by E.ON and the UK Green Investment Bank.

Project Type

Offshore wind farm

Location

English Channel, Sussex coast

Capacity

400MW

Estimated Investment

$2.9bn approximately

Expand

Rampion wind turbines

Rampion Offshore Wind Project is being developed in the English Channel, 13km off the coast of Sussex in south-east England. The project is being developed by E.ON and the UK Green Investment Bank.

To be spread over 72km², the wind farm will have an initial capacity to generate 400MW of electricity that will be sufficient to supply for up to 290,000 homes.

The project will be jointly owned by E.ON (50.1%), UK Green Investment Bank (25%) and Enbridge (24.9%). E.ON will invest approximately £1.3bn ($2bn), UK Green Investment Bank will invest £236m ($370m) and Enbridge will invest £370m ($570m) in the project. The wind farm is expected to have an operational life of 25 years.

The project is expected to create approximately between 250 and 300 jobs during the three-year offshore construction phase, while 100 people will be employed in the onshore cable route construction and between 40 and 60 jobs will be created for the onshore substation construction.

The wind farm will further generate 65 permanent jobs at the operations and maintenance base, when fully operational.

Rampion offshore wind project background

The Crown Estate awarded the exclusive right for the development of the Rampion wind project to E.ON in January 2010. The proposed project received approval from the Secretary of State for Energy and Climate Change in July 2014. It will be the first offshore wind farm off the south coast of England.

The final layout increased the distance between the closest turbine and the Heritage Coast by two-fold, and decreased the field of view by a third when compared to the original layout.

The layout averts the ‘9miler’ dredging fishing area as well as anchorage and straight passage of the Shoreham Port.

Rampion wind farm make-up and construction

The wind farm will be equipped with 116 Vestas V112-3.45MW wind turbines of 3.45MW capacity each. The turbines will be installed at a minimum distance 750m from each other and connected by means of inter array cables. Each turbine will have a hub height of 84m and a height of 140m to blade tip.

An operations and maintenance base for the project will be constructed at Newhaven port. It will include office space, equipment storage and vessel mooring facilities. The project will also include an offshore substation and an export cable path.

Following the receipt of approval to begin construction in May 2015, the onshore construction for the substation began in June 2015. The installation of turbine foundations is expected to begin in January 2016. The offshore construction is scheduled for completion in 2018.

Access points will be constructed to allow the construction of a haul road along the cable route.

Contractors involved with the offshore wind project

“To be spread over 72km², the wind farm will have an initial capacity to generate 400MW of electricity that will be sufficient to supply for up to 290,000 homes.”

E.ON is responsible for the construction, operations and maintenance as well as energy management services of the wind farm.

ABB was awarded a turnkey contract to provide onshore substation, and power infrastructure for the offshore platform of the wind farm in June 2015. The contractual scope includes the delivery of the onshore substation comprising high-voltage air-insulated switchgear (AIS), gas-insulated switchgear (GIS), transformers and substation automation as well as control and protection systems.

ABB will also provide medium-voltage switchgear, power transformers and protection and control systems for the offshore platform as well as two new switchgear bays with control and protection equipment for the National Grid’s substation at Bolney.

JDR Cable Systems was awarded a contract to supply subsea cabling technology and services for the wind farm in May 2015. The contract includes the supply of cable cleats, connectors, hang-offs, cable protection system and 142km of 36kV inter array cables.

Carillion was awarded a contract for civil engineering and cable installation. The onshore cabling works are expected to be completed by the end of 2016.

MHI Vestas Offshore Wind was contracted to supply and install the turbines. Fugro was contracted for the installation and burial of 122 inter array cables, which will be performed in two phases between 2016 and 2017.

Related Projects

Nysater Wind Farm

Nysäter project is a 475MW wind park being developed in Sweden. It will be the second-largest onshore wind farm in…

Mundra Power Plant, Gujarat

The Mundra power plant is a 4,620MW coal-based thermal power station in the Kutch district of Gujarat in India. It…

XXL (Weesow-Willmersdorf) Solar Park

XXL (Weesow-Willmersdorf) solar park is a 187MW solar project being developed in Brandenburg, Germany. It will be the largest solar…