View all newsletters
Receive our newsletter - data, insights and analysis delivered to you
  1. Project
7 April 2010

The Ross Island Wind Farm Project, Antarctica

The Ross Island Wind Farm (RIWF) resulted from the construction and integration of a small three-turbine wind farm on Cr
Crater Hill Wind Farm viewed from Pressure Ridges in front of Scott Base.
Turbine WEC1 hub and blades being lifted into position.
Turbine WEC3 hub and blades.
An aerial view of the turbines of Ross Island wind farm.
Backfilling in 200mm layers and compacting around Site T3 Foundation Blocks with screened material previously excavated.
Frequency converter (26,000lbs, 11.8t) flown to site on USAP C-17 transport to facilitate 2008/09 summer season network commissioning.
Wind turbine blades being transported to McMurdo Station Gap lay down area for winter storage.
Summer southerly storm creates a challenge getting access to wind turbine components, McMurdo Station Gap lay down area.

The Ross Island Wind Farm (RIWF) resulted from the construction and integration of a small three-turbine wind farm on Crater Hill, Ross Island, Antarctica. The 0.99MW wind farm is the southern-most wind farm in the world. It supplies power to and links the electrical grids of both New Zealand’s Scott Base and the US’ McMurdo Station.

Free Report
img

Wind Power Market seeing increased risk and disruption

The wind power market has grown at a CAGR of 14% between 2010 and 2021 to reach 830 GW by end of 2021. This has largely been possible due to favourable government policies that have provided incentives to the sector. This has led to an increase in the share of wind in the capacity mix, going from a miniscule 4% in 2010 to 10% in 2021. This is further set to rise to 15% by 2030. However, the recent commodity price increase has hit the sector hard, increasing risks for wind turbine manufacturers and project developers, and the Russia-Ukraine crisis has caused further price increase and supply chain disruption. In light of this, GlobalData has identified which countries are expected to add the majority of wind power capacity out to 2030. Get ahead and download this whitepaper for more details on the current state of the Wind Power Market.
by GlobalData
Enter your details here to receive your free Report.

The purpose of the project is to offset power generation diesel-fuel consumption at the two research stations on Ross Island, Antarctica. The three turbines are predicted to save 11% of the fuel used annually to provide electricity on Ross Island.

The project was funded by the New Zealand Government and built under an alliance between Antarctica New Zealand (AntNZ) and Meridian Energy Ltd (Meridian) with support from the US National Science Foundation (NSF). The alliance was tasked with the procurement, construction, commissioning, operation and maintenance of the RIWF.

Stage 1 of the RIWF was designed to be a “proof of concept” project demonstrating the supply of wind energy in extreme polar conditions. If proven successful, subsequent proposed wind project stages could offset up to 40%-50% of the fuel used for power generation.

RIWF project details

The project was initiated in early 2005 when Meridian was invited by AntNZ to assess the wind generation potential for supplying Scott Base. The Crater Hill site, located nearly halfway between the two bases, was identified as the preferred site and a wind-monitoring mast was constructed.

“The 0.99MW Ross Island wind farm is the southern-most wind farm in the world.”

Discussions were held with NSF, which under the US Antarctic Program had been investigating wind energy supply for McMurdo Station. In August 2007, Meridian presented a project proposal to AntNZ and NSF, which was accepted.

The funds for the project were obtained in September 2007. The wind farm was planned to be constructed over two Antarctic summer seasons (November to February).

The focus of the 2008/09 season was to construct the wind turbine foundations, electrically connect the two bases and transport all the wind turbine equipment to site.

The second season in 2009/10 saw the wind turbines constructed and commissioned in December 2009, followed by system optimisation testing in February 2010. The farm was officially opened in January 2010.

Ross Island wind farm details

RIWF employs three Enercon E33 wind turbines, each with a capacity of 0.33MW. The first turbine of the wind farm became operational in December 2009, and at full load, had more than twice the capacity to supply Scott Base’s total load of 150kW, allowing the Scott Base diesel generators to become silent.

Wind farm construction

The construction of the wind farm began in November 2008. The project was unique compared to other wind farms as work could only be carried out during summer, when there was access to the site in the polar region.

“The wind project could offset up to 40%-50% of the fuel used for power generation.”

The key engineering innovation was the construction of the foundations that support the wind turbines.

Due to sub-zero temperatures, no concrete manufacturing facilities or the availability of aggregate and fresh water, it was not possible to employ the typical wind turbine gravity pad foundation. Instead, a pre-fabricated foundation was designed and built in New Zealand and shipped to the site.

Each foundation was built by using eight 13t pre-cast concrete blocks frozen into the permafrost.

The blocks were laid in a circular fashion in an excavated area and refilled so that the tops of the blocks are nearly flush with the ground. A steel spider foundation with eight legs was then bolted to each block of the foundation.

The towers of the turbines were fixed on top of the laid steel structure. The work involving installation of the turbines was carried out during late 2009.

The installation of power systems between Scott Base and US McMurdo Station was also carried out during the construction.

Wind farm transmission

The power generated by the RIWF will be transmitted to New Zealand’s Scott Base operating at 50Hz and the American base at McMurdo Station operating at 60Hz.

The power transmission will be carried out through an electrical grid consisting of ground-laid cables connecting the wind farm to Scott Base and the base at McMurdo station. The turbines generate electricity at 60Hz and a static frequency converter was installed at Scott Base to convert the electricity to 50Hz for use.

In addition, the system also includes a flywheel system that ensures stability. The flywheel can absorb or supply 500kW for 30 seconds to maintain the system frequency during sudden wind changes.

Environmental protection

“The energy produced through the fossil fuels is being substituted by the renewable wind energy generated by the wind farm.”

The Antarctic Treaty principles of environmental protection were incorporated in the project development. The operator is also focusing on reducing the environmental impacts of the wind farm’s operations.

The three wind turbines of RIWF will cut down the diesel fuel required by the bases by 463,000l and reduce the carbon dioxide emissions by 1,242t per annum.

The energy produced through the fossil fuels is being substituted by the renewable wind energy generated by the wind farm. The replacement not only reduces the greenhouse gases but also reduces the risk related to the transportation and storage of liquid fuel on Ross Island.

In addition, developments pertaining to the further reduction of fuel consumption and greenhouse gas emissions at the bases by up to 40-50% are under investigation.

Topics in this article:
NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU

Thank you for subscribing to Power Technology