Projects

Taweelah A1 Power and Desalination Plant, Abu Dhabi

The Taweelah A1 plant was refurbished and expanded to 385 million litres per day of clean water and 1,430MW.

Plant type
Combined cycle gas turbine
Location
Abu Dhabi, United Arab Emirates
Estimated investment
$1.5bn
Commissioning
1 May 2003
Fuel
Natural gas
Turbines and HRSGs
Three GE 9E and five combined cycle 9E gas turbines, eight HRSGs
Desalination units
Three 202.7MW back pressure steam turbines

The Taweelah A1 plant was refurbished and expanded to 385 million litres per day of clean water and 1,430MW. In July 2001, Abu Dhabi Water and Electricity Authority (ADWEA) signed a contract with TotalFinaElf and Tractebel for the purchase, expansion and refurbishment of the plant. The four-year project to expand the facility (one of the biggest cogeneration plants in the world) was completed in 2006. Further expansion is now planned.

The contract was for $1.5bn, and the plant was commissioned on 1 May 2003 on time and within budget. ADWEA signed a long-term contract to buy power and water from the plant, which meets about a quarter of Abu Dhabi’s water and power needs.

Power and water demand in the Middle East

The Arab world has one of the highest demands for power generation and clean water due to high population growth rates and economic diversification efforts.

Estimates in early 2002 showed that there were 20 ongoing and planned projects in the Middle East alone worth over $10bn, including Taweelah A1. The average annual increase in demand in the Arab world is 6% compared to the 3% global average. The United Arab Emirates is planning to add 8,000MW during this decade.

The Gulf Cooperation Council estimated $100bn of investment would be necessary over the ten years, which is why it moved more towards private investment. UAE and Oman have been the leading countries in developing the private sector in Build-Operate-Transfer (BOT) and Build-Own-Operate (BOO) projects.

Upgrade and extension at Taweelah

The three GE 9E co-generation gas turbines were equipped with bypass stacks so that they can be operated in high-pressure single or combined cycle modes. There were also five new combined cycle 9E gas turbines.

The original three Heat Recovery Steam Generators (HRSG) were replaced with eight standardised pieces of equipment and three new steam turbines that receive steam from the HRSGs via a common header. Three new 202.7MW back-pressure steam turbines were added to supply steam for the desalination units.

Four of the existing Multi-Stage Flash (MSF) desalination units were upgraded to eight million gallons per day each, and 14 Multi-Effect Distillation (MED) desalination units added 3.77 million gallons (14 million litres) per day each. The potable water storage tanks were upgraded to a total capacity of 80 million gallons (300 million litres) per day.

Taweelah A1 supplies water for farms, tree plantations and parks that are part of the government’s irrigation and development programme. High voltage electricity cables of 132kV and 400kV were installed to the Transco grid station.

Further expansion planned

In February 2007, Gulf Total Tractebel (GTTPC) announced a further extension of Taweelah A1, together with the refinancing of its existing debt. GTTPC is 60% owned by Gulf Power Company and 40% by Total Tractebel Emirates Power Company (Total SA 50%, SUEZ-Tractebel S.A. 50%).

Taweelah A1 had an original production capacity of 1,360MW and 380,000m³ per day. From May 2009, the extension will increase the total power capacity to 1,592MW. The extension will be for a turnkey construction contract from Doosan Heavy Industries & Construction Co. Ltd.

There will be a six-year extension of the power and water agreement until 2029 for the whole plant, as well as amended financing arrangements under better terms and conditions for GTTPC and its shareholders. The refinancing is costing $1,102.5m with a maturity of approximately 22.5 years. It was arranged with a syndicate of 23 international banks, with BNP Paribas and Calyon acting as the Initial Mandated Lead Arrangers/Underwriters.

Finance and subcontractors

In 1999 and 2000, ADWEA negotiated the contracts for Taweelah A1, and final agreements were made in December 2001. The agreement involved the sale of the original plant from ADWEA to Gulf Total Tractebel (60% Gulf Power Company, 20% Tractebel, the energy subsidiary of Suez Lyonnaise des Eaux, and 20% TotalFinaElf).

Tractebel signed a €280m contract with Vivendi for desalination equipment to provide potable water. It supplied 14 desalination units at 17,150m³/d to produce a total of 240,000m³/d. Seawater is desalinated using a process of multiple effect and compression.

Babcock Borsig Power (BBP), now taken over by Babcock Power, won a €410m contract for the five GE gas turbines, three steam turbines and the eight boilers. It supplied the eight heat recovery boilers through its then subsidiary, NEM.

“There will be a six-year extension of the power and water agreement until 2029 for the whole Taweelah plant.”

BBP Services provided piping, installation and maintenance of the auxiliary boilers and firing systems. Another subsidiary, Oberhausen, supplied the air condensers, and another the electrical and control engineering.

Norton Rose was the intermediary for the financing that was agreed in December 2001 between ADWEA, BNP Paribas and Citibank NA. Consultants to ADWEA during the agreement process included SCFB, Fichtner, White and Case and Al Tamini.

Maintenance and revision

All desalination and power block equipment was revised by the engineering firm Sargent and Lundy throughout 2002/03. It included comparisons of power and water purchase agreements, site construction progress, fuel use compared to performance and payment of contractors.

GE International supplied the long-term maintenance contracts for the plant for parts repairs, field services and upgrades of the GE Frame 9E gas turbine generators and the eight GE Frame DLN machines.

The Dolphin project

The Taweelah plants are on the receiving end of a pipeline from the Dolphin Gas Project. The first phase was a $3.5bn development for the easy provision of natural gas to a number of receiving terminals via a 48in-diameter, 350km pipeline. It is estimated that the full cost was $10bn.

Halliburton Brown and Root designed and constructed the gas transmission pipeline, the gas receiving and metering facilities at Taweelah and a riser platform. The Dolphin Project transports 2 billion ft³/d (56 million m³/d) of natural gas.

Related Projects

Datan Power Plant Expansion, Taoyuan

Taiwan’s largest natural gas-fired combined-cycle power plant, Datan (also known as Tatan or Dah-Tarn power plant), is located in Taoyuan…