View all newsletters
Receive our newsletter - data, insights and analysis delivered to you
  1. Project
21 February 2016

Veja Mate Offshore Wind Farm Project

The Veja Mate offshore wind farm is located 130km north of Eemshaven, in the German Exclusive Economic Zone of the North Sea.
Veja Mate offshore wind farm location map. Credit: Volker Stevin International.
The wind farm will be installed with 67 offshore wind turbine generators. Credit: Volker Stevin International.
The Seajacks Scylla vessel will be delivered to the client in March 2016. Credit: Volker Stevin International.
The Scylla vessel will be equipped with a Huisman 1,500t leg-encircling crane. Credit: Volker Stevin International.

The Veja Mate offshore wind farm is located 130km north of Eemshaven, in the German Exclusive Economic Zone of the North Sea. The project is owned by the Highland Group, Siemens Financial Services and Copenhagen Infrastructure Partners.

Free Report
img

Wind Power Market seeing increased risk and disruption

The wind power market has grown at a CAGR of 14% between 2010 and 2021 to reach 830 GW by end of 2021. This has largely been possible due to favourable government policies that have provided incentives to the sector. This has led to an increase in the share of wind in the capacity mix, going from a miniscule 4% in 2010 to 10% in 2021. This is further set to rise to 15% by 2030. However, the recent commodity price increase has hit the sector hard, increasing risks for wind turbine manufacturers and project developers, and the Russia-Ukraine crisis has caused further price increase and supply chain disruption. In light of this, GlobalData has identified which countries are expected to add the majority of wind power capacity out to 2030. Get ahead and download this whitepaper for more details on the current state of the Wind Power Market.
by GlobalData
Enter your details here to receive your free Report.

It will produce more than 1.6TWh of green, renewable electricity a year, which is equivalent to the annual consumption of approximately 400,000 German homes and is expected to offset more than 18 million tonnes of CO₂ from the atmosphere.

Veja Mate offshore wind farm make-up

The Veja Mate offshore wind farm will be installed with 67 Siemens SWT-6.0-154 direct drive wind turbines supported by monopiles installed at water depths between 39m and 41m. The turbines have a rated capacity of 6MW each, rotor diameter of 154m and hub height of 80m above sea level. The location witnesses an average wind speed of more than 10m/s.

The monopiles, with a diameter of 7.8m and weighing approximately 1,300t, will be fabricated by EEW at Rostock, Germany, whereas the transition pieces will be fabricated by Bladt Industries at Aalborg, Denmark.

Construction of the Veja Mate project

Construction of the Veja Mate offshore wind park project will begin with foundation installation, which is expected in April 2016. The seabed preparation work at the offshore site began in February 2016. The turbine installation will commence in March 2017 and be completed by the end of 2017. The project is expected to be fully operational by January 2018.

Contractors involved with the Veja Mate offshore wind project

Siemens was awarded a turbine supply and 15-year service and maintenance contract in July 2015. Seajacks UK was contracted to provide the Seajacks Scylla installation vessel for the transport and installation of the monopiles in the same month.

Royal Boskalis Westminster (Boskalis) was awarded a contract worth €500m ($557.89m) for the design, procurement, fabrication, supply, transportation, installation and testing of the foundations for the wind farm in a 50% partnership with VolkerWessels (Volker Stevin International) in June 2015.

Volker Stevin International will provide the design and engineering services for the permanent works and the handling tools during the transport and installation of the foundations. JDR will deliver hang-offs, connectors and a range of other cable accessories as well as providing topside termination and testing services.

Smulders was contracted to provide design, production, transportation and installation of a topside and jacket for the offshore wind farm. Sormec was contracted to supply a M350/3S telescopic boom crane for the offshore wind farm in October 2015.

EMS Maritime Offshore was awarded the contract to guard the offshore wind farm with its fleet of guard vessels. SMC was contracted to deliver full-scope marine coordination and vessel management on the project.

Veja Mate grid connection

“The turbines have a rated capacity of 6MW each, rotor diameter of 154m and hub height of 80m above sea level.”

The wind farm will be connected to the power grid through the existing BorWin 2 offshore substation, which was built by Siemens for TenneT.

CG, an Avantha Group Company, in association with other consortium partners Cofely Fabricom and Iemants, was awarded a contract for the turnkey supply and installation of a high-voltage offshore substation for the project in May 2015. The contractual scope included connecting the turbines to the German high-voltage grid via the BorWin2 converter platform. The substation is based on Overdick’s MOAB platform concept.

Siem Offshore Contractors (SOC) was awarded a €100m ($111.83m) contract for the turnkey supply and installation package of the inner-array grid cable system in April 2015.

Financing for the Veja Mate project

The final investment decision for the Veja Mate project was made in July 2015. The project is being financed through a combination of equity and debt. It is supported financially by eight international lenders, including Eksport Kredit Fonden and KfW, contributing up to €1.275bn ($1.42bn) debt.

KfW contributed €430m ($478.89m) for the offshore wind farm project under the Offshore Wind Energy Programme established in 2011.

K2 Management was selected as technical advisors, Green Giraffe as the financial advisor and CMS as the advisor for legal structuring as well as project financing.

Topics in this article:
NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU

Thank you for subscribing to Power Technology