Gok 2 is a 35.75MW onshore wind power project. It is located in Manisa, Turkey. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in August 2014.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Onshore | 35.75 | 35.75 | – | Active | Manisa, Turkey | GARET Enerji Uretim ve Ticaret |
---|
Description
The project was developed by GARET Enerji Uretim ve Ticaret. Gama Enerji, Gama Guk Sistemleri Muhendislik ve Taahhut and GAMA Holding are currently owning the project having ownership stake of 96%, 1% and 1% respectively.
The project generates 123,000MWh of electricity. The project cost is $67.425m.
Development Status
The project is currently active. The project got commissioned in August 2014.

US Tariffs are shifting - will you react or anticipate?
Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.
By GlobalDataContractors Involved
GE Renewable Energy was selected as the turbine supplier for the wind power project. The company provided 13 units of 2.75-103 turbines, each with 2.75MW nameplate capacity.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.