SGS Industrial Services GmbH completed the mechanical installation of two Gas Turbine Combined Cycle Units with a total capacity of 841MW for the Czech energy supplier CEZ in Pocerady (CZ) in September 2012.

The SGS scope of work comprised installation of two Siemens gas turbine and generator systems, including noise enclosures and a Minimax fire-fighting system.

The installation works started in February 2012, SGS managed to fulfil the ambitious and challenging time schedule.

At the moment SGS supports the commissioning of the power plant. Operations at the plant are scheduled to start around mid-2013.