Fukuyama Steam Turbine Power Plant is a 720.25MW gas fired power project. It is located in Hiroshima, Japan. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 1970. Buy the profile here.
Description
The project is co-owned by JFE Steel and The Chugoku Electric Power, with their respective ownership stake of 50% each.
It is a Steam Turbine power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is blast furnace gas. In case of shortage of blast furnace gas the plant can also run on Coke Oven Gas.
Development status
The project got commissioned in 1970.
Contractors involved
Fukuyama Steam Turbine Power Plant (Fukuyama Steam Turbine Power Plant Unit III) is equipped with Toshiba Energy Systems and Solutions steam turbine. The phase consists of 1 steam turbine with 163MW nameplate capacity.
Fukuyama Steam Turbine Power Plant (Fukuyama Steam Turbine Power Plant Unit IV) is equipped with Toshiba Energy Systems and Solutions steam turbine. The phase consists of 1 steam turbine with 163MW nameplate capacity.
Fukuyama Steam Turbine Power Plant (Fukuyama Steam Turbine Power Plant Unit V) is equipped with Toshiba Energy Systems and Solutions steam turbine. The phase consists of 1 steam turbine with 163MW nameplate capacity.
Toshiba Energy Systems and Solutions supplied electric generator for the Fukuyama Steam Turbine Power Plant (Fukuyama Steam Turbine Power Plant Unit III).
Toshiba Energy Systems and Solutions supplied electric generator for the Fukuyama Steam Turbine Power Plant (Fukuyama Steam Turbine Power Plant Unit III).
Toshiba Energy Systems and Solutions supplied electric generator for the Fukuyama Steam Turbine Power Plant (Fukuyama Steam Turbine Power Plant Unit IV).
Toshiba Energy Systems and Solutions supplied electric generator for the Fukuyama Steam Turbine Power Plant (Fukuyama Steam Turbine Power Plant Unit IV).
Toshiba Energy Systems and Solutions supplied electric generator for the Fukuyama Steam Turbine Power Plant (Fukuyama Steam Turbine Power Plant Unit V).
Toshiba Energy Systems and Solutions supplied electric generator for the Fukuyama Steam Turbine Power Plant (Fukuyama Steam Turbine Power Plant Unit V).
Mitsubishi Power supplied steam boiler for the Fukuyama Steam Turbine Power Plant (Fukuyama Steam Turbine Power Plant Unit III).
Mitsubishi Power supplied steam boiler for the Fukuyama Steam Turbine Power Plant (Fukuyama Steam Turbine Power Plant Unit III).
Mitsubishi Power supplied steam boiler for the Fukuyama Steam Turbine Power Plant (Fukuyama Steam Turbine Power Plant Unit IV).
Mitsubishi Power supplied steam boiler for the Fukuyama Steam Turbine Power Plant (Fukuyama Steam Turbine Power Plant Unit IV).
Mitsubishi Power supplied steam boiler for the Fukuyama Steam Turbine Power Plant (Fukuyama Steam Turbine Power Plant Unit V).
Mitsubishi Power supplied steam boiler for the Fukuyama Steam Turbine Power Plant (Fukuyama Steam Turbine Power Plant Unit V).
For more details on Fukuyama Steam Turbine Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.