Colorado Bagasse Cogeneration Project is a 56.715MW biopower project. It is located in Sao Paulo, Brazil. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in 1981.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Biopower 56.715 56.715 Active Sao Paulo, Brazil

Description

The project is currently owned by Acucar e Alcool Oswaldo Ribeiro de Mendonca with a stake of 100%.

Bagasse which is a kind of agricultural by-product is used as a feedstock to power the project.

The project consists of 1 turbine with 2.56MW nameplate capacity.

The project consists of 1 turbine with 3.655MW nameplate capacity.

GlobalData Strategic Intelligence

US Tariffs are shifting - will you react or anticipate?

Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.

By GlobalData

The project consists of 1 turbine with 6MW nameplate capacity.

The project consists of 1 turbine with 6.5MW nameplate capacity.

Development Status

The project got commissioned in 1981.

Contractors Involved

Siemens was selected as the steam turbine supplier for the project. The company provided 1 unit of SST600 turbine with 38MW nameplate capacity.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.