AES Parana Combined Cycle Power Plant is an 845MW gas fired power project. It is located in Buenos Aires, Argentina. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in November 2001. Buy the profile here.

Description

The project is currently owned by AES Argentina Generacion with a stake of 100%.

It is a Combined Cycle Gas Turbine (CCGT) power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Diesel.

The project generated 5,583,708MWh of electricity.

Development status

The project got commissioned in November 2001.

Contractors involved

Mitsubishi Power was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of Axial Flow steam turbine with 319MW nameplate capacity.

Mitsubishi Power was selected as the turbine supplier for the Gas fired project. The company provided 2 units of M701F gas turbines, each with 263MW nameplate capacity.

Mitsubishi Power supplied electric generator for the project.

Mitsubishi Power supplied steam boiler for the project.

For more details on AES Parana Combined Cycle Power Plant, buy the profile here.