Cikarang Listrindo Combined Cycle Power Plant is a 646MW gas fired power project. It is located in West Java, Indonesia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 1993. Buy the profile here.

Smarter leaders trust GlobalData

Report-cover

Data Insights Cikarang Listrindo Combined Cycle Power Plant

Buy the Profile

Data Insights

The gold standard of business intelligence.

Find out more

Description

The project is currently owned by PT Cikarang Listrindo with a stake of 100%.

It is a Combined Cycle Gas Turbine (CCGT) power plant. The fuel is procured from PT Pertamina Gas.

Development status

The project got commissioned in 1993.

Contractors involved

Cikarang Listrindo Combined Cycle Power Plant (Cikarang Listrindo Combined Cycle Power Plant Block I Phase I) is equipped with GE Power 6B.03 gas turbines. The phase consists of 2 gas turbines with 30MW nameplate capacity.

Cikarang Listrindo Combined Cycle Power Plant (Cikarang Listrindo Combined Cycle Power Plant Block I Phase II) is equipped with GE Power 6B.03 gas turbines. The phase consists of 4 gas turbines with 30MW nameplate capacity.

Cikarang Listrindo Combined Cycle Power Plant (Cikarang Listrindo Combined Cycle Power Plant Block I Phase III) is equipped with Mitsubishi Power steam turbines. The phase consists of 2 steam turbines, each with 60MW nameplate capacity.

Cikarang Listrindo Combined Cycle Power Plant (Cikarang Listrindo Combined Cycle Power Plant Block II Phase I) is equipped with GE Power Frame 9 gas turbine. The phase consists of 1 gas turbine with 109MW nameplate capacity.

Cikarang Listrindo Combined Cycle Power Plant (Cikarang Listrindo Combined Cycle Power Plant Block II Phase II) is equipped with GE Power Frame 9 gas turbine. The phase consists of 1 gas turbine with 109MW nameplate capacity.

Cikarang Listrindo Combined Cycle Power Plant (Cikarang Listrindo Combined Cycle Power Plant Block II Phase III) is equipped with Siemens steam turbine. The phase consists of 1 steam turbine with 128MW nameplate capacity.

GE Power supplied electric generator for the Cikarang Listrindo Combined Cycle Power Plant (Cikarang Listrindo Combined Cycle Power Plant Block I Phase I).

GE Power supplied electric generator for the Cikarang Listrindo Combined Cycle Power Plant (Cikarang Listrindo Combined Cycle Power Plant Block I Phase II).

Mitsubishi Power supplied electric generator for the Cikarang Listrindo Combined Cycle Power Plant (Cikarang Listrindo Combined Cycle Power Plant Block I Phase III).

GE Power supplied electric generator for the Cikarang Listrindo Combined Cycle Power Plant (Cikarang Listrindo Combined Cycle Power Plant Block II Phase I).

GE Power supplied electric generator for the Cikarang Listrindo Combined Cycle Power Plant (Cikarang Listrindo Combined Cycle Power Plant Block II Phase II).

Siemens supplied electric generator for the Cikarang Listrindo Combined Cycle Power Plant (Cikarang Listrindo Combined Cycle Power Plant Block II Phase III).

GE Power supplied steam boiler for the project.

For more details on Cikarang Listrindo Combined Cycle Power Plant, buy the profile here.

This content was updated on 14 October 2024

Data Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.