Dandong Power Plant is a 700MW coal fired power project. It is located in Liaoning, China. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in January 1999. Buy the profile here.
Description
The project is currently owned by Huaneng Power International with a stake of 100%.
It is a Steam Turbine power plant. The fuel is procured from Northern Shanxi Province.
The project generated 2,920,000MWh of electricity.
Development status
The project got commissioned in January 1999.
Power purchase agreement
The power generated from the project is sold to State Grid Liaoning Electric Power under a power purchase agreement.
Contractors involved
Mitsubishi Power was selected as the turbine supplier for the Coal fired project. The company provided 2 units of TC2F-38.6 steam turbines, each with 350MW nameplate capacity.
Siemens Energy supplied electric generator for the project.
Siemens Energy supplied electric generator for the project.
Siemens Energy supplied electric generator for the project.
Doosan Babcock Energy supplied steam boiler for the project.
Doosan Babcock Energy supplied steam boiler for the project.
Doosan Babcock Energy supplied steam boiler for the project.
For more details on Dandong Power Plant, buy the profile here.