Guojin Power Plant is a 700MW coal fired power project. It is located in Shanxi, China. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in September 2015. Buy the profile here.
Description
The project is developed and owned by Shanxi Guojin Electricity. The company has a stake of 100%.
It is a Steam Turbine with Cogen power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is coal. In case of shortage of coal the plant can also run on Bituminous Coal.
The project cost is $762.473m.
Development status
The project got commissioned in September 2015.
Contractors involved
Dongfang Electric was selected as the turbine supplier for the Coal fired project.
Dongfang Boiler Group supplied steam boiler for the project.
Dongfang Boiler Group supplied steam boiler for the project.