Hintermuhr is a 104MW hydro power project. It is located on schmalzgraben river/basin in Salzburg, Austria. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1988 and subsequently entered into commercial operation in 1991. Buy the profile here.

Description

The project is currently owned by Salzburg.

Hintermuhr is a pumped storage project. The gross head of the project is 601.35m. The project generated 180 GWh of electricity.

The hydro power project consists of 1 turbine with 36MW nameplate capacity.

Development status

The project construction commenced in 1988 and subsequently entered into commercial operation in 1991.

Contractors involved

Andritz Hydro was selected as the turbine supplier for the hydro power project. The company provided 1 unit of pump turbine with 68MW nameplate capacity.

Andritz Hydro supplied electric generator(s) for the project. The generator capacity is 78 MVA.

For more details on Hintermuhr, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.