View all newsletters
Receive our newsletter - data, insights and analysis delivered to you
  1. Project
15 July 2014

Alta Wind Energy Center (AWEC), California

Alta Wind Energy Center (AWEC), also known as Mojave Wind Farm, is the second-largest onshore wind energy project in the world. It is owned by Terra-Gen Power.
Alta Wind Energy Center (AWEC) is the second largest onshore wind farm in the world.
AWEC is located just two miles from the Tehachapi Wind Resource Area (WRA), which consists of wind farms constructed in the 1970s and 80s. Image courtesy of Ham Pastrami.
The AWEC will consist of up to 600 turbines in total.
Unit I of AWEC is installed with GE 1.5-MW SLE turbines.
Vestas is supplying its V90-3.0MW turbines for the Alta Wind Energy Center.

Alta Wind Energy Center (AWEC), also known as Mojave Wind Farm, is the second-largest onshore wind energy project in the world. It is owned by Terra-Gen Power, an affiliate of Arclight Capital Partners and Global Infrastructure Partners.

Free Report
img

Wind Power Market seeing increased risk and disruption

The wind power market has grown at a CAGR of 14% between 2010 and 2021 to reach 830 GW by end of 2021. This has largely been possible due to favourable government policies that have provided incentives to the sector. This has led to an increase in the share of wind in the capacity mix, going from a miniscule 4% in 2010 to 10% in 2021. This is further set to rise to 15% by 2030. However, the recent commodity price increase has hit the sector hard, increasing risks for wind turbine manufacturers and project developers, and the Russia-Ukraine crisis has caused further price increase and supply chain disruption. In light of this, GlobalData has identified which countries are expected to add the majority of wind power capacity out to 2030. Get ahead and download this whitepaper for more details on the current state of the Wind Power Market.
by GlobalData
Enter your details here to receive your free Report.

The project will supply 1,550MW of clean renewable energy to Southern California Edison (SCE) for more than 25 years under a 3,000MW wind power development initiative upon completion. The purchase agreement was signed in 2006.

Spread across 3,200 acres in the foothills of the Tehachapi Mountains in Kern County, AWEC is located just two miles from the Tehachapi wind resource area (WRA), which consists of wind farms constructed in the 1970s and 1980s. The turbines were installed at altitudes ranging from 3,000ft to 6,000ft above sea level in Tehachapi.

The first phase of AWEC began in July 2010. It consisted of units I to V, which were completed in April 2011. Construction of units VI and VIII began in early 2011 and was completed in late 2011, and building of the units VII and IX started in April 2012 and was completed in December 2012. The Units X and XI were completed in 2013.

Terra-Gen’s AWEC development

Terra-Gen took over the Alta project from Australian infrastructure fund Allco Finance Group after the company discontinued its ‘Alta – Oak Creek Mojave’ initiative because of bankruptcy in the early 2000s.

Terra-Gen offered $325m to the company for acquiring the project.

The project will include the installation of up to 600 wind turbines, serving the needs of 257,000 California homes after the completion. Construction and installation of some 300 turbines are expected to start in 2015 and will generate approximately 830MW.

Construction of California’s wind power site

The AWEC project comprises installation of up to 600 wind turbines and construction of supporting facilities, a batching plant, service roads, a power collection system, transmission lines (both overhead and underground), electrical switchyards and substations.

“The project will include the installation of up to 600 wind turbines, serving the needs of 257,000 California homes after the completion.”

Other infrastructure includes communication cables with data input monitored by a SCADA system, meteorological towers, a lightning protection system and other operations and maintenance facilities.

The transmission line includes a single six-mile-long 230kV line, connecting the SCE’s Windhub substation.

Graders and power haulers are used for transferring the turbines to the project site.

Generating capacity of the Alta Wind Energy Center

The first phase of AWEC consisting of units I to V became operational in April 2011. Unit I has an installed capacity of 150MW and was the first unit to be connected to the Windhub substation. Unit I is installed with GE 1.5-MW SLE turbines.

Units II to V have installed capacity of 150MW, 150MW, 102MW and 168MW respectively. The four units are installed with Vestas V 90-3.0MW turbines.

Construction of units VI and VIII began in January 2011. The two units have an installed capacity of 150MW each and use Vestas V 90-3.0MW turbines.

The installation of a total of 100 turbines for the two units was completed by late 2011.

Units VII and IX also use the same Vestas turbines and the construction work on them started in April 2012. Their completion increased the generating capacity of the AWEC to 1,320MW, while the completion of units X and XI brought the total capacity to 1,547MW.

Financing the Californian wind farm

Financing for the $394m unit I of AWEC was completed in March 2010. It consisted of a seven-year construction and term loan, a bridge loan to the Investment Tax Credit (ITC), cash grants from the US Department of Energy and other supporting credit facilities.

Credit Agricole CIB and Nataxis of New York branch-led the financing with the other lenders being the Union Bank, Prudential Investment Management, Robobank Nederland and Banco Santander.

Financing for the $1.2bn units II to V was completed in July 2010. The four units were financed by Citibank, Barclays Capital and Credit Suisse. Google invested $55m in May 2011 in unit IV and $102m in unit V in June 2011. Citibank also invested in unit V.

Financing for the $631m units VI and VIII was completed in June 2011, comprising of a seven-year construction and term loan, a bridge loan to the Investment Tax Credit (ITC) cash grant from the US Department of Treasury and other supporting credit facilities. It was led by Credit Agricole Corporate and Investment Bank, as well as the MUFG Power Utilities Group.

ING Capital, Robobank, Santander and RBS Securities were the joint arrangers for the funds, while the lenders included CoBank, Bank of Motreal, Key Bank, Lloyds, DZ Bank and Helaba.

Financing with a similar structure was arranged for the $650m units VII and IX in April 2012. The financing process was led by Union Bank (an affiliate of Mitsubishi-UFJ Financial Group) and RBA Securities. The joint lead arrangers were Bank of Montreal, Canadian Imperial Bank of Commerce, Key Bank, KfW IPEX Bank and Santander, while the lenders were Sumitomo, BayernLB, DZ Bank and Associated Bank.

Alta Wind Energy Center (AWEC) contractors

The unit was acquired by GE and Bankers Commercial with shares of 50% each in 2011.

Blattner Energy was responsible for leading the construction of units VI and VIII, which were completed by late 2011.

Unit VI of AWEC was sold to EverPower, a subsidiary of Terra Firma, in April 2012, while Unit VIII was sold to Brookfield.

Blattner Energy was also responsible for the construction work of units VII and IX as well as units X and XI.

Topics in this article:
NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU

Thank you for subscribing to Power Technology