View all newsletters
Receive our newsletter - data, insights and analysis delivered to you
  1. Project
4 May 2018

Lagoa do Barro Wind Complex, Piaui

The 195MW Lagoa do Barro windfarm is being developed approximately 580km from the city of Teresina in the northeast Brazilian state of Piauí.
The Lagoa Do Barro wind complex will generate 195MW of clean energy. Credit: Atlantic Energias Renováveis.
An 88.1km-long transmission line is being built to distribute power generated at the wind complex. Credit: Atlantic Energias Renováveis.
Construction on the Lagoa Do Barro wind farm began in June 2017. Credit: Atlantic Energias Renováveis.
The transmission line for the Lagoa Do Barro complex will require 203 lattice metal structures. Credit: Atlantic Energias Renováveis.
The wind turbines for the project are being supplied by Acciona Windpower. Credit: Acciona.

The 195MW Lagoa do Barro windfarm is being developed approximately 580km from the city of Teresina in the northeast Brazilian state of Piauí.

Free Report
img

Wind Power Market seeing increased risk and disruption

The wind power market has grown at a CAGR of 14% between 2010 and 2021 to reach 830 GW by end of 2021. This has largely been possible due to favourable government policies that have provided incentives to the sector. This has led to an increase in the share of wind in the capacity mix, going from a miniscule 4% in 2010 to 10% in 2021. This is further set to rise to 15% by 2030. However, the recent commodity price increase has hit the sector hard, increasing risks for wind turbine manufacturers and project developers, and the Russia-Ukraine crisis has caused further price increase and supply chain disruption. In light of this, GlobalData has identified which countries are expected to add the majority of wind power capacity out to 2030. Get ahead and download this whitepaper for more details on the current state of the Wind Power Market.
by GlobalData
Enter your details here to receive your free Report.

A joint venture between Atlantic Energias Renováveis and Actis, a private equity firm based in the UK and a shareholder of Atlantic, is developing the project at an estimated cost of R$1.3bn ($416.78m).

Spread across an area of 2,854ha, the wind complex comprises eight windfarms, namely Lagoa do Barro I to VII, and Queimada Nova. Operations of the windfarm are expected to begin by the end of 2018.

The project is expected to create 500 direct and indirect jobs to locals during the peak construction period.

Lagoa do Barro windfarm make-up

The Lagoa do Barro wind complex will feature a total of 65 AW125/3000 turbines rated at 3MW each. The turbines will have a rotor diameter of 125m and will be mounted on 120m-high concrete towers.

The turbines will have a six-pole, double feeding generator with a frequency range of 50/60Hz and will operate at a speed of 700rpm-1,300rpm at 50Hz, and 840rpm-1,560rpm at 60Hz.

Certified to IEC IIb wind class, the turbines can survive medium wind speeds with lower turbulence intensity. The cut-in and cut-out wind speeds of the turbine are 3.5m/s and 25m/s respectively.

Lagoa do Barro wind complex construction

Atlantic Energias Renováveis signed an agreement with Piaui’s Institute of Lands (Interpi) for the use of land to develop the wind complex in April 2016. The project secured installation licenses in November 2016, following which the construction works commenced in June 2017.

“It will support the Government of Brazil’s national strategy to diversify its energy matrix by generating 10GW of electricity from renewable sources by 2018.”

The nacelles and blades of the turbines were manufactured at external sites in December 2017.

Internal roads of 45km length were constructed to link the eight wind parks of the complex. Excavation works for 56 of 65 foundations were completed as of April 2018.

A tower factory was built on an area of 7ha within the wind complex for the production of 1,500 concrete components to support the construction of the wind turbines. It was inaugurated in April 2018.

Grid connection

An 88.1km-long, 230kV transmission line is being constructed from the Lagoa do Barro 1 substation to the Sao Joao do Piaui substation to transmit the power generated at the project. The substations will feed the power to the Brazilian national grid.

Pre-assembly on the transmission line, which will require 203 lattice metal structures, began in November 2017.

Financing for Lagoa do Barro wind project

Inter-American Investment Corporation (IIC), a member of Inter-American Development Bank (IDB), is evaluating a proposal to offer a R$430m ($137.8m) loan for the project.

The loan will be offered through either the IDB Group Partial Guarantee covering the senior loan and infrastructure debentures for a 12-year tenor, or a long-term loan facility on a 15-year door-to-door tenor basis.

Contractors involved

Acciona Windpower, a company owned by Nordex Group, secured a contract to supply the 65 turbines in March 2015. The company will also operate and maintain the turbines for 15 years, under the contract.

Benefits of the Lagoa do Barro windfarm

The Lagoa do Barro wind project is expected to reduce the country’s dependency on fossil fuels. It will support the Government of Brazil’s national strategy to diversify its energy matrix by generating 10GW of electricity from renewable sources by 2018.

It is also expected to reduce carbon emissions and generate revenue for state and local governments.

Topics in this article:
NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU

Thank you for subscribing to Power Technology