Projects

Musandam Independent Power Project (IPP)

Musandam Independent Power Project (IPP) is a 120MW gas-fired power plant developed by Musandam Power Company (MPC) in the Musandam region of northern Oman.

Plant Type
Gas-fired power plant
Location
Oman
Installed Capacity
120MW
Production Started
November 2017
Owner/Developer
Musandam Power Company
Contractors
Wartsila, Sarooj Construction Company

Musandam Independent Power Project (IPP) is a 120MW gas-fired power plant developed by Musandam Power Company (MPC) in the Musandam region of northern Oman. The project sources natural gas from the adjacent Musandam gas processing plant (MGP).

MPC is a joint venture between Oman Oil Company (OOC, 70%) and LG International Corp (30%). It was established as Oman’s first independent power producer in the Musandam Governorate.

The project was originally scheduled for commissioning by October 2016 but was officially inaugurated in November 2017.

The project generates 120MW of electricity, replacing the diesel-based electricity generation in the Governorate of Musandam. It is operated and managed by Wartsila under a 15-year operation and maintenance agreement with MPC.

Musandam IPP background

Oman Power and Water Procurement Company (OPWP) appointed advisors, including Ernst and Young (Financial), Curtis Mallet-Prevost (Legal), Poyry, and Worley Parsons (Technical) to conduct a feasibility study to develop a new gas-fired power plant in December 2011.

The pre-qualification process for engineering, procurement and construction (EPC) contractors was concluded in April 2013. A power purchase agreement (PPA) was signed with OPWP and a natural gas supply agreement was approved with the Oman Ministry of Oil and Gas in August 2015.

Financial closure for the project was achieved with Bank Muscat in the same month.

Musandam IPP make-up

The Musandam project occupies an area of 80,000m² located adjacent to the OOCEP Musandam Gas Plant on a coastal site near the Musandam/Ras Al Khaimah (RAK) border crossing. It uses natural gas as the primary fuel for generation of electricity, while fuel oil is used as backup fuel.

The smart power generation plant, supplied by Wartsila, includes 15 Wartsila 34DF engines and is capable of responding to load variations between 10MW and 120MW.

The plant is designed to operate at extreme temperatures of up to 50°C and deliver superior performance in highly humid conditions. The plant also suites island mode operations and does not require much water for cooling.

Musandam power plant construction

Construction of the MPP began with the laying of the foundation stone for the plant in October 2015. The power plant and the main substation were built on the platform. The total cut volume of the project is 2.52 million metres cubed and the concrete volume is 1,000m³.

Earthworks for the project included the removal of mountain materials of approximately 2.5 million metres cubed. The rocks were broken using pneumatic, hydraulic breakers and explosives.

“The plant is designed to operate at extreme temperatures of up to 50°C and deliver superior performance in highly humid conditions.”

An environmental impact assessment (EIA) of the project found the presence of coral reefs in the area. Silt curtains were installed to stop the mud migration towards the corals. A quarry run of approximately 1.2 million metres cubed was dumped and a revetment comprising two layers of rock was provided to protect the area.

Retaining walls were built considering the landscape, dimensions and levels of the plot. Gabion walls were constructed to retain rockfall from mountain sides, while reinforced concrete walls were also built for additional protection around the structures.

Grid connection

The electricity generated from the project is transmitted to the existing medium-voltage grid through the new 132KV transmission lines built by the Rural Area Electricity Company SAOC.

Contractors involved

Wartsila was chosen as the EPC contractor and long-term service provider for the project in December 2014.

Sarooj Construction Company (SCC) was awarded the EPC subcontract by Wartsila to perform enabling works.

Related Projects

Datan Power Plant Expansion, Taoyuan

Taiwan’s largest natural gas-fired combined-cycle power plant, Datan (also known as Tatan or Dah-Tarn power plant), is located in Taoyuan…