Bauer – Pontiac Line – Upgrade – 345 kV – Phase I is a 345kV overhead line from Bauer, Michigan, the US, to Pontiac, Michigan, the US.
The project, which is currently in the planning stage, is expected to be commissioned in 2022.
Description
Bauer – Pontiac Line – Upgrade – 345 kV – Phase I is an overhead line that will be operated by ITC Holdings. The line will carry alternating current (AC) through single circuit cable.
Approximately $0.96m was financed by the authorities to undertake the construction works of the project.
Bauer – Pontiac Line – Upgrade – 345 kV – Phase I project development status
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataThe construction works on the Bauer – Pontiac Line – Upgrade – 345 kV – Phase I project will be commenced in 2021 and commissioning is expected in 2022.
About ITC Holdings
ITC Holdings Corp (ITC Holdings), a subsidiary of ITC Investment Holdings Inc, is an independent electricity transmission company. It owns, operates, maintains, and invests in electricity transmission infrastructure and grid solutions. The company provides transmission and grid solutions to improve reliability, expand access to markets, allow new generating resources to interconnect to its transmission systems and reduce the cost of supplying energy. The company owns and operates high-voltage electric transmission systems in Lower Peninsula of Michigan and certain portions of Iowa, Kansas, Illinois, Missouri, Minnesota and Oklahoma.
Methodology
All publicly-announced T&D Line & Substation projects included in this analysis are drawn from GlobalData’s Power IC. The information regarding the projects is sourced through secondary information sources such as country specific utility players, company news and reports, statistical organisations, regulatory body, government planning reports and their publications and is further validated through primary from various stakeholders such as power utility companies, consultants, energy associations of respective countries, government bodies and professionals from leading players in the power sector.