Eshkol Combined Cycle Power Plant is a 775MW gas fired power project. It is located in South, Israel. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in December 2005.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 775 | 775 | – | Active | South, Israel |
---|
Description
The project is currently owned by The Israel Electric.
It is a Combined Cycle Gas Turbine (CCGT) power plant that is used for Baseload. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Diesel.
Development Status
The project got commissioned in December 2005.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataContractors Involved
The Israel Electric was selected to render EPC services for the gas fired power project.
Eshkol Combined Cycle Power Plant (Eshkol Combined Cycle power plant Block I) is equipped with GE Power 9FA gas turbine. The phase consists of 1 gas turbine.
Eshkol Combined Cycle Power Plant (Eshkol Combined Cycle power plant Block II) is equipped with Doosan Skoda Power MTD50CA steam turbine. The phase consists of 1 steam turbine with 138MW nameplate capacity.
Eshkol Combined Cycle Power Plant (Eshkol Combined Cycle power plant Block II) is equipped with Siemens SGT5-4000F gas turbine. The phase consists of 1 gas turbine with 260MW nameplate capacity.
GE Power supplied electric generator for the Eshkol Combined Cycle Power Plant (Eshkol Combined Cycle power plant Block I).
Siemens supplied Air Cooled electric generator for the Eshkol Combined Cycle Power Plant (Eshkol Combined Cycle power plant Block II).
GE Power supplied steam boiler for the Eshkol Combined Cycle Power Plant (Eshkol Combined Cycle power plant Block I).
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.