Datang Anyang Power Plant is a 600MW coal fired power project. It is located in Henan, China. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in August 2009. Buy the profile here.
Description
The project is currently owned by Henan Branch.
It is a Steam Turbine with Cogen power plant. The fuel is procured from Hemei Group.
Development status
The project got commissioned in August 2009.
Contractors involved
Dongfang Turbine was selected as the turbine supplier for thermal power project. The project consists of 2 units of C300 / 235-16.7 / 0.343 / 537/537 turbines, each with 300MW nameplate capacity.
DEC Dongfang Electric Machinery supplied QFSN 300-2-20B electric generator for the Datang Anyang Power Plant (Datang Anyang Power Plant Unit I).
DEC Dongfang Electric Machinery supplied QFSN-300-2-20 electric generator for the Datang Anyang Power Plant (Datang Anyang Power Plant Unit II).
Dongfang Boiler Group supplied steam boiler for the Datang Anyang Power Plant (Datang Anyang Power Plant Unit I).
Dongfang Boiler Group supplied steam boiler for the Datang Anyang Power Plant (Datang Anyang Power Plant Unit II).
For more details on Datang Anyang Power Plant, buy the profile here.