Munera II is a 30.6MW onshore wind power project. It is located in Castile-La Mancha, Spain. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in July 2007. Buy the profile here.
Description
The project is developed and owned by EDP Renovaveis. The company has a stake of 100%.
The project cost is $66.28m.
Development status
The project is currently active. The project got commissioned in July 2007.
Contractors involved
Vestas Wind Systems was selected as the turbine supplier for the wind power project. The company provided 17 units of V90-1.8 MW turbines, each with 1.8MW nameplate capacity.
Ingeteam Corporacion and Vestas Wind Systems were contracted to render operations & maintenance services for the project.
For more details on Munera II, buy the profile here.
About EDP Renovaveis
EDP Renovaveis SA (EDPR), a subsidiary of Energias de Portugal SA, is a renewable energy company. It develops, builds and operates wind farms and solar plants. The company also offers a wide range of services in the project lifecycle, including site identification, renewable resource analysis, obtainment of permit, design layout, contract, funding, construction, commencement of operation, delivery of energy, maintenance service, data analysis and dismantling. EDPR has interests in various projects in under development phase and in pipeline. It has operational presence in Europe, South America, and North America. EDPR is headquartered in Madrid, Spain.