Sloy is a 152.5MW hydro power project. It is located on Loch Lomond river/basin in Scotland, the UK. The project is currently active. It has been developed in single phase. The project construction commenced in 1945 and subsequently entered into commercial operation in 1950.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Hydropower | 152.5 | 152.5 | – | Active | Scotland, the UK | SSE Generation |
---|
Description
The project was developed by SSE Generation and is currently owned by SSE.
Sloy is a reservoir based project. The gross head of the project is 277m. The total number of penstocks, pipes or long channels that carry water down from the hydroelectric reservoir to the turbines inside the actual power station, are 4 in number. Sloy underwent through rehabilitation & modernization during 1990-1999. The project generated 130 GWh of electricity.
Development Status
The project construction commenced in 1945 and subsequently entered into commercial operation in 1950.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataContractors Involved
The English Electric was selected as the turbine supplier for the hydro power project. The company provided 1 unit of francis turbine with 32.5MW nameplate capacity.
The English Electric was selected as the turbine supplier for the hydro power project. The company provided 3 units of francis turbines, each with 40MW nameplate capacity.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.