View all newsletters
Receive our newsletter - data, insights and analysis delivered to you
  1. Project
29 January 2015

Clashindarroch Wind Farm, Aberdeenshire, Scotland

Clashindarroch Wind Farm is a 36.9MW onshore renewable power project developed by Vattenfall in Clashindarroch Forest, near Huntly, Aberdeenshire, Scotland, UK.
The 36.9MW Clashindarroch wind farm is located in Clashindarroch Forest, Aberdeenshire, Scotland. Credit: Simon Price.
Construction of the £60m ($94m) wind project began in June 2013. Credit: Simon Price.
The wind farm produced first power on 22 January 2015. Credit: Simon Price.

Clashindarroch Wind Farm is a 36.9MW onshore renewable power project developed by Vattenfall in Clashindarroch Forest, near Huntly, Aberdeenshire, Scotland, UK.

Free Report
img

Wind Power Market seeing increased risk and disruption

The wind power market has grown at a CAGR of 14% between 2010 and 2021 to reach 830 GW by end of 2021. This has largely been possible due to favourable government policies that have provided incentives to the sector. This has led to an increase in the share of wind in the capacity mix, going from a miniscule 4% in 2010 to 10% in 2021. This is further set to rise to 15% by 2030. However, the recent commodity price increase has hit the sector hard, increasing risks for wind turbine manufacturers and project developers, and the Russia-Ukraine crisis has caused further price increase and supply chain disruption. In light of this, GlobalData has identified which countries are expected to add the majority of wind power capacity out to 2030. Get ahead and download this whitepaper for more details on the current state of the Wind Power Market.
by GlobalData
Enter your details here to receive your free Report.

The £62m ($94.72m) wind project received planning consent from Aberdeenshire Council in late 2010 and construction began in June 2013. Turbine installation was completed in September 2014 and the wind farm produced first power on 22 January 2015.

When fully commissioned, the wind power facility is estimated to produce more than 110GWh of renewable energy a year, which will be enough to meet the annual electricity needs of approximately 27,000 households. It is also expected to offset 40,000t of CO₂ emissions a year during its 20-year operational life.

Wind turbines at the Clashindarroch wind farm

The Clashindarroch Wind Farm consists of 18 Senvion MM82 onshore wind turbines installed across an area of approximately 4km². Each of the 2.05MW turbines has a rotor diameter of 82m, blade length of 40m, rotor surface of 5,281m² and wing-tip height of 110m. The rotor speeds range from 8.5rpm to 17.1rpm and make the turbines ideal for high-wind locations.

The Senvion MM82 pitch-regulated variable speed turbines are mounted on 69m-high towers weighing 122t.

Grid connection for the Clashindarroch wind farm

The power generated by the wind turbines is transmitted, via underground cables, to a new substation built by Scottish and Southern Energy next to the A920 road at Cairnford. The electricity is stepped up by a 33kV/275kV transformer at the substation and connected to the existing 275kV overhead line to be fed to the national grid.

Construction details of the wind farm in Aberdeenshire

Construction of the Scottish wind farm began with the tree clearance works by the Forestry Commission Scotland and their contractors. A total of 412ha of forest land was cleared and was followed by building 30.5km of access roads to each turbine location.

A reinforced concrete foundation and a crane hard standing were then prepared at each of the 18 turbine locations. Steel reinforcements were installed in the excavation and shuttering was placed at the base to retain the concrete. Each foundation required approximately 300m³ of concrete pouring with the use of long-reaching pumps. Screed rails were used to attain accuracy while pouring the concrete to the desired level.

The poured concrete was allowed to set after the application of a smooth finish. The final section to receive concrete was the upstand section to which the turbine was later bolted. Shuttering was placed around this section and removed once the concrete set. A steel float finish was then given to the concrete foundation and the gap around was backfilled up to 100mm below the top of the upstand section.

Turbines towers, in segments of three, were built at a facility in Chepstow. The Senvion factory in Germany manufactured the turbine blades, which were shipped to the Port of Inverness. The turbine components, including tower sections, gears, generators, nacelle and blades, were transported by road to the site and installed section by section.

Two cranes were employed to lift the tower sections upright, lower them into position and, finally, bolt them into place.

Contractors involved with the Clashindarroch wind project

German wind turbine manufacturer Senvion (formerly REpower Systems), a wholly-owned subsidiary of Suzlon Group, was contracted to supply and install the turbines for the renewable power project in September 2013.

The civil engineering contract for the project was awarded to RJ Mcleod, a construction firm based in Dingwall, Scotland. The scope of work included construction of access roads, foundations and hard standings for the wind turbine installation.

Chepstow-based company Mabey Bridge was awarded a contract to supply the turbine towers in November 2013.

Topics in this article:
NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU

Thank you for subscribing to Power Technology