Construction on Lake Winds Energy Park commenced in November 2012. Image courtesy of Consumers Energy.
Local construction workers installing reinforcement bars on the wind turbine tower foundation. Image courtesy of Consumers Energy.
First section being placed at its base. Image courtesy of Consumers Energy.
Construction workers hired by sub contractor Davis JD Steel of Phoenix busy pouring concrete for the foundation. Image courtesy of Consumers Energy.
A total of 56 wind turbine generators, each of 1.8MW capacity, will be installed across an area of around 15 square miles. Image courtesy of Consumers Energy.
Installation of the second blade. The wind farm will use Vestas V100 wind turbine generators to produce green energy. Image courtesy of Consumers Energy.
The wind park will start producing clean, renewable, wind-generated electricity by the fourth quarter of 2012. Image courtesy of Consumers Energy.

Lake Winds Energy Park, Mason County, Michigan, US

Lake Winds Energy Park is an onshore wind farm being built in southern Mason County in Michigan, US. The power station will deliver up to 100MW of green electricity to consumers. It is expected to be commissioned in October 2012.

The project is being developed and will be operated by Consumers Energy, a division of CMS Energy and supplier of natural gas and electricity in Michigan. It is the first wind power project of Consumers Energy.

The wind farm’s development is estimated to have cost $235m, of which approximately 75% will be spent on purchasing construction stuffs, wind turbines and towers, substation equipment, transformers and other capital equipment.

Purpose of Michigan’s new wind farm

"Mason County was chosen for the construction of Lake Winds wind farm after examining 18 other potential sites in Michigan."

Consumers Energy is honoured for being the largest supplier of green energy in Michigan. Approximately five percent of the electricity that it supplies in the state is generated from renewable sources.

In 2007, the company, in its 25-year Balanced Energy Plan, committed to achieve ten percent of its power supplies from renewable sources by 2015. In order to achieve this, the company decided to harness the state’s wind energy and hence planned to build two wind farms in Michigan.

The first wind farm, being set up in Mason County, will enable Consumers Energy to generate eight percent of its total electricity from renewable sources.

The second wind farm, Cross Winds Energy Park, will be built in Tuscola County. The 150MW facility, when commissioned in 2015, will allow the company to meet or exceed the state’s mandated goal of ten percent by 2015.

Reasons for choosing Mason County

Mason County was chosen for the construction of Lake Winds wind farm after examining 18 other potential sites in Michigan. The selected site, which includes Riverton and Summit Townships located in southern Mason County, offers unrestricted exposure to wind resources. Availability of a readily usable electric transmission grid also worked in favour of Mason County.

Moreover, Mason County has wind ordinance in place which takes care of public safety and at the same time offers flexibility in building productive wind-based power station.

Details of the Lake Winds onshore wind farm

The Lake Winds project includes installation of 56 Vestas V100-1.8MW turbines. The turbines are designed as per the specifications of International Electrotechnical Commission Standard 61400-1 (IEC 61400-1).

"The power station will deliver up to 100MW of green electricity to consumers."

The turbines will be installed across an area of around 15 square miles in the Riverton and Summit Townships. About 18% of the 56 wind turbine generators will be located in Summit Township, with the remainder in Riverton Township.

Each wind turbine generator will be fastened to a 95m high tubular steel tower. The overall height of the entire setup will be 145m, including blade length.

A Supervisory Control and Data Acquisition (SCADA) system will be installed to supervise and control the wind turbines. Though the turbines can be operated and controlled remotely, there will be full-time turbine technicians for onsite support.

Substation and grid network connections

The wind turbine generators will be connected to a new substation via a network of 34.5kV underground transmission lines. The transmission cables will be laid at least 48in below the ground so that they will not interfere with agricultural practices.

The substation, to be built on 5.2 acres of land in Summit Township, will escalate the voltage from 34.5kV to a transmission voltage of 138kV. The stepped-up current will be transmitted to the nearby grid connection point at Pere Marquette Highway.

Contractors involved with Lake Winds Energy Park


Related project


Alta Wind Energy Center (AWEC), California, United States of America

Alta Wind Energy Center (AWEC), also known as Mojave Wind Farm, is the second largest onshore wind energy project in the world.


Vestas-American Wind Technology was contracted in July 2010 to supply the wind turbines for the project.

The engineering, procurement and construction (EPC) contract for the Lake Winds project was awarded to White Construction, a wholly owned subsidiary of Infrastructure and Energy Alternatives (IEA), in November 2010.

The scope of the EPC contract includes construction of all slip roads, modification and or upgradation of existing county roads, design and construction of all foundations, design and installation of a substation, installation of underground electrical cables and the erection of wind turbines. Site restoration work will be undertaken after completion of construction.

The Mexican transformer manufacturer Prolec GE, a joint-venture between Xignux and General Electric (GE), was contracted in November 2010 to supply electric transformers for the new substation.