View all newsletters
Receive our newsletter - data, insights and analysis delivered to you
  1. Project
17 December 2021

Viking Energy Wind Farm, Shetland Islands, UK

The Viking Energy wind farm on Shetland Islands in Scotland is expected to come online in 2024.

The 443MW Viking Energy wind farm is being developed on the Shetland Islands in Scotland, UK, by SSE Renewables, a renewable energy subsidiary of SSE.

Free Report
img

Wind Power Market seeing increased risk and disruption

The wind power market has grown at a CAGR of 14% between 2010 and 2021 to reach 830 GW by end of 2021. This has largely been possible due to favourable government policies that have provided incentives to the sector. This has led to an increase in the share of wind in the capacity mix, going from a miniscule 4% in 2010 to 10% in 2021. This is further set to rise to 15% by 2030. However, the recent commodity price increase has hit the sector hard, increasing risks for wind turbine manufacturers and project developers, and the Russia-Ukraine crisis has caused further price increase and supply chain disruption. In light of this, GlobalData has identified which countries are expected to add the majority of wind power capacity out to 2030. Get ahead and download this whitepaper for more details on the current state of the Wind Power Market.
by GlobalData
Enter your details here to receive your free Report.

Upon completion, the project is expected to be one of the biggest onshore wind farms by output in the UK. With a capacity to generate approximately 2TWh of energy a year, it is estimated to power 475,098 homes a year and offset 500,000t of carbon emissions a year.

SSE Renewables is investing £580m ($790.6m) in the wind farm. The financial investment decision (FID) was made in June 2020. Construction of the project began in August 2020 while concrete was poured for the first turbine at Mid Kame hills, Shetland Islands, in September 2021.

The wind farm is expected to be commissioned in late 2024. It is predicted to generate up to 400 jobs during the construction phase, and an additional 35 jobs upon commissioning.

Viking Energy wind farm location

The Viking wind farm is being built on the central mainland of Shetland, on a site extending between Scatsta in the north, and Weisdale in the south.

The site is divided into four quadrants, namely Delting, Collafirth, Kergord, and Nesting.

Viking Energy wind farm make-up

The wind farm will include 103 Vestas V117-4.2 MW turbines, each with a generating capacity of 4.3MW. The turbine is expected to provide high performance and durability to help realise the full potential of the wind farm. The model is designed to withstand extreme wind conditions.

Designed for medium to high wind speeds, each turbine has a swept area of 10,751m² (115,722ft²) and a rotor diameter of 117m. The onshore turbine has a blade length of 57.2m while the cut-in and cut-out wind speeds are 3m/s and 25m/s, respectively.

Power transmission of the Viking Project

The power generated by the Viking Energy wind farm will be fed into the electricity grid through the Shetland HVDC link, a 600MW high-voltage direct current (HVDC) transmission link connecting Shetland to the UK mainland via a 260km-long subsea cable. It will be the anchor project for the transmission link, which was approved by the office of gas and electricity markets (Ofgem), the UK government energy regulator, in July 2020.

The HVDC system will include a 320/132kV substation, a HVDC converter station, and a HVDC switching station, which will be connected to the existing transmission system at Noss Head in Caithness.

Contractors involved

Danish wind turbine maker Vestas was selected as the turbine supplier for the Viking Energy project in August 2020. The company will supply, install, and commission the turbines. It will also supply VestasOnline Business SCADA, a solution that aims to reduce the downtime of the turbines and optimise the production. The company is also expected to provide long-term services to the wind farm once it is operational.

Scottish civil engineering company RJ McLeod was awarded the civil construction contract for the wind farm in July 2020.

Ground investigations for the project were conducted by BAM Ritchies, a ground engineering division of the UK-based construction and civil engineering company BAM Nuttall. The investigations were supported by Frank L Johnston, MBEC Environmental Consulting, Lerwick Port Authority, geotechnical consultant Natural Power, helicopter operator PDG Aviation Services, and Headland Archaeology.

An independent planning monitoring officer from Ramboll UK was engaged to support the environmental monitoring process of the project.

Civil engineering firm Tulloch Developments was contracted to build an access track to Upper Kergord in February 2020. The track connects Upper Kergord to the HVDC converter station, which is required for the transmission link to the mainland.

French cable manufacturer Nexans was selected to supply 800km of 33kV underground cables for the wind farm in June 2021. The cables will be used for linking the wind turbine arrays together and exporting the generated power to the main substation. The electricity from the substation will be fed into the interconnector, where it will then be transmitted for to the national grid.

Viking Energy wind project background

The Shetland community was previously involved in the development of the wind farm through a joint venture (JV) with SSE.

Shetland Islands Council and SSE signed a partnership agreement for the development of a wind farm in Shetland in 2007. An application for a wind power project with 150 turbines was submitted to the Scottish government in 2009.

The partners filed a revised application to reduce the number of turbines to 103 in 2010. The government approved this in 2012.

The consent for the wind farm was challenged in court by environmental activists. The legal action was unsuccessful, although it delayed the development of the project for several years.

The developers sought to increase the maximum tip height of the turbines from 145m to 155m in 2018, to enable the deployment of the latest wind turbine models for increased power generation. The application for the increased tip height was approved in May 2019.

SSE gained full ownership of the wind farm in 2019. The community is entitled to receive annual returns on its historic investment in the development of the project, once operational.

Topics in this article:
NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU

Thank you for subscribing to Power Technology