The Wambo wind farm in Queensland, Australia, is being developed in two stages. Credit: Cubico Sustainable Investments & Stanwell Corporation Limited.
The project will have a total of 83 V162-6.2MW wind turbines upon completion. Credit: Cubico Sustainable Investments & Stanwell Corporation Limited.
The wind farm is expected to be commissioned within 2026. Credit: Cubico Sustainable Investments & Stanwell Corporation Limited.

The Wambo wind farm is a 506.2MW onshore wind project under construction in the Western Downs region of Queensland, Australia.

The project is being developed in two stages by a 50:50 joint venture between Cubico Sustainable Investments and Queensland government-owned energy company Stanwell.

The construction of the wind farm was officially launched with a ground-breaking ceremony held in June 2023. The first stage commenced operations in the second quarter (Q2) of 2026, while the second stage is expected to be completed by the end of the year.

The wind farm is expected to produce sufficient electricity to power up to 312,000 households and offset up to 1.1 million tonnes per annum (mtpa) of carbon dioxide emissions. The operational life of the wind farm is expected to be 30 years.

Location and site details of Wambo wind farm

The Wambo wind farm is located 15km north-east of Jandowae in the Western Downs region of Queensland, Australia.

Situated north-west of Dalby, the project site lies within Queensland’s 2,000MW Southern Renewable Energy Zone in the Western Downs and near Stanwell’s Tarong power stations.

Wambo wind farm development details

Development works started with the ecological field investigation in November 2019.

Planning approval for a 500MW wind farm along with a 50MW/200MWh battery storage and associated infrastructure was granted by the Queensland government in October 2020.

The project received approval from the federal government under the Environment Protection and Biodiversity Conservation (EPBC) Act 1999 in January 2022.

Wambo wind farm make-up

Stage one of the Wambo wind farm project involves the installation of 42 Vestas EnVentus V162-6.2MW wind turbines with a capacity of 6MW each for a total capacity of 252MW.

The second stage will add 41 additional turbines with the same capacity of 6.2MW each, adding another 254.2MW capacity to the project and cumulating to a total installed capacity of approximately 506.2MW.

The EnVentus V162-6.2MW wind turbines feature a rotor diameter of 162m, a turbine height of 247m from base to tip and a swept area of 20,612m² (221,866ft²). Designed to operate efficiently across a broad range of wind conditions, the turbines combine high output with low noise levels.

Construction details of the Wambo wind farm

Site establishment works for stage one of the wind farm started in April 2023. The first turbine components were delivered to the project site in October 2024.

Stage two construction commenced in April 2024. By April 2026, all 83 turbines for the project were on site, with delivery of the final 41 turbines as part of stage two.

Energisation and commissioning of the first group of six turbines commenced in May 2025, followed by the first generation and transmission to the Queensland grid in the following month of June.

Grid connection from the Wambo wind farm

The wind farm is proposed to be connected to the existing transmission corridor from Tarong to Chinchilla through a 275kV transmission line, which will connect the new substation at the wind farm site to Powerlink’s Halys Substation located 11km south-east of the Kumbia township.

State-owned electricity transmission system operator Powerlink Queensland is responsible for connecting the project to the Queensland transmission network.

Powerlink began construction in early 2023 to connect the wind farm’s first stage to the transmission network. The work was completed in late 2024. To support the second stage, Powerlink expanded the Diamondy Substation, which was completed in March 2026.

The electricity generated by the wind farm will be fed into the Queensland SuperGrid, which is being developed as part of the Queensland Energy and Jobs Plan to boost grid capacity and storage by connecting the solar, wind, battery, and hydrogen projects across the state.

The wind farm is further planned to be connected to the 2GW Borumba pumped hydro project being developed at Lake Borumba, located west of the Sunshine Coast in southern Queensland. The Borumba project is expected to be commissioned in 2032.

Financing details of the Wambo wind farm

Stanwell was allocated A$192.5m ($128.5m) from the Queensland government’s Renewable Energy and Hydrogen Jobs Fund for its 50% share of investment in the Wambo wind project in March 2022.

Offtake agreements

Stanwell will offtake 100% of the power generated from both stages of the project under a 15-year power purchase agreement (PPA).

Contractors involved

Danish wind turbine manufacturer Vestas is responsible for the engineering, procurement and construction (EPC) and supply of 83 wind turbines for the project. It will also provide operations and maintenance services for the project for at least 30 years.

Environmental Resources Management Australia performed environmental studies for the project.

Construction company Fulton Hogan was engaged as the civil balance of plant contractor for stage one of the project. Civil-engineering company Beibly was engaged for the second phase.

Australian energy and utility services provider Yurika was contracted for electrical balance of plant for both stages of the project. The company subcontracted OCU Group to deliver underground electrical reticulation for the wind farm. All Energy Contracting was subcontracted for the underground electrical reticulation network across both project stages.

Insulect provided electrical infrastructure across stages one and two. The delivery comprised 33kV disconnectors and post insulators for internal collection, alongside 275kV disconnectors and post insulators, among other equipment for the transmission network.

Engineering and environmental consulting company Stantec was contracted to assess the wind farm’s traffic impacts and recommend mitigation measures.

Nathan Contractors provided civil and foundation construction support, including wind turbine tower base pours.

Oestermark Grouting, Y-MatTec, BRAWG Industry Solutions, 343 Consultants, Borger Cranes, and Gulati Transport are some of the other contractors involved in the Wambo wind farm project.