London Array Offshore Wind Farm, United Kingdom




Key Data


Construction on the world’s largest offshore wind farm began in July 2009. The plant is located around 15km from the Kent and Essex coasts in the outer Thames Estuary, UK. It will see up to 341 turbines in an area of up to around 245km² on and between the Long Sand and Kentish Knock sandbanks.

The whole project costs around £3bn, and is being developed by a consortium called London Array Limited. This initially had three partners: Shell WindEnergy, E.ON and DONG Energy. In July 2008, though, Shell pulled out it committed to leave its staff in the project until the end of the year. Shell has been replaced by Masdar and has a 20% stake in the project while DONG Energy and E.ON have a 50% and 30% stake respectively.

E.ON Climate & Renewables operates three offshore wind farms with an overall generation capacity of 83MW, with a further 200MW currently under construction.

The wind farm will be constructed in phases. The first phase of the project is expected to become operational by last quarter of 2012 and will generate 630MW.

When complete, the wind farm will meet the electricity needs of 750,000 homes – around a quarter of Greater London or all of the homes in Kent and East Sussex. It will displace 1.9 million tons of carbon-dioxide each year. It generates nearly 7% of the UK Government's renewable energy target of providing 15.4% of the UK's electricity from renewable sources by 2015.

London Array applied for the various planning consents and licences in June 2005, following extensive environmental studies, which began in 2001. A variety of planning consents and licences were needed, from different consenting bodies. Onshore, the consents included the substation, access road and changes to overhead lines. Offshore, they included the wind farm itself, as well as offshore substations and cables.

The Department for Business, Enterprise and Regulatory Reform is the main government department responsible for administering applications for offshore wind farms. It works with other departments and statutory consultants, including the Department for Environment, Food and Rural Affairs (Defra). An approval from the Department for BERR was also needed to support overhead line works for the proposed onshore substation at Cleve Hill near Graveney.

An environmental impact assessment addressed the possible effects on birds, fish, mammals and the seabed ecology. It also assessed the effects on shipping and navigation, boat traffic and coastal processes, along with visual and noise impacts. Responsibility for granting planning permission for the proposed onshore substation at Cleve Hill (and the electricity cables from the onshore substation to the mouth of the Swale) lies with Swale Borough Council and Canterbury City Council.

London Array Offshore Wind Farm Details

Onshore construction began in July 2009 and offshore construction is scheduled to begin in the first quarter of 2011. Power generation is expected to begin in the last quarter of 2012.

The site has high wind speeds, a low water depth and suitable ground conditions. 341 turbines will be needed, along with the foundations securing them to the sea bed. The turbines will be grounded in an area of up to 245km² on and between the Long Sand and Kentish Knock sand banks.

A monopile foundation will be used for phase one. Array cabling will connect groups of turbines and offshore substations, which will step up the voltage to reduce losses before feeding the power to shore. Up to six undersea export cables will connect the offshore transformers and the shore.

"The London Array site has high wind speeds, a low water depth and suitable ground conditions."

The Siemens SWT-3.6 turbine will generate 3.6MW. The hub height will be between 80m and 90m above sea level, and the total turbine height will not be greater than 175m. The turbines will have three blades. The turbines will be painted grey, with a bright colour band on the lower part of the turbine to increase the visibility of the turbines to boats. In addition, navigation lights, markings and red aircraft warning lights will be installed to meet safety requirements. The distance between the maximum sea level and tip of the blade will be more than 22m to minimise risk of damage to crafts.

They will typically begin generating electricity at a minimum wind speed of 3m/s, with full power being achieved from 13m/s. For safety reasons they will begin to shut down at wind speeds greater than 25m/s (a force 9 gale).

Distribution

The onshore substation will be connected to the National grid's 400kV transmission system. The substation construction began in August 2007 after a public enquiry.

Contracts

MPI will supply state-of-the-art vessel MPI Adventure, to ship cables and install more foundations and turbines compared to the boats."

First tier suppliers for construction of first phase for 630MW were announced on December 2009. Contracts to supply marine crew and vessels have been awarded to MPI and A2SEA and a €100m power cable contract has been given to Nexans. Siemens will be supplying 175 SWT-3.6MW turbines to the onshore substations.

MPI will supply state-of-the-art vessel MPI Adventure, to ship cables and install more foundations and turbines compared to the boats. A jack-up barge will be supplied by A2SEA, which is expected to be on site by March 2011.

In addition to supplying the turbines, Siemens will also provide the instrumentation and control equipment for the project. It will also conduct the design and grid access studies.

Finance

The project came under cash crunch after Shell Energy withdrew itself from the project due to economic crisis in 2008. The project received financial backing from European Investment Bank (EIB) for £3bn, which is the total cost of the project.

UK Power Market

UK has an installed capacity of 35,602MW and can grow as much as 31.3% by 2015-2016. Britain uses various sources for power generation. In 2009, around 38.1% of electricity in the country was generated through coal and 37.5% through gas. The rest (23.86%) was generated from nuclear and renewable energy.

There is intense pressure from the government to reduce carbon gas emissions from the coal-fired plants as they emit three times more carbon than the gas-fired plants. The government has advised cutting carbon emissions by 50% by 2050 to avoid dangerous climate change. It has introduced regulations to source energy from renewable sources. Currently, the UK generates only 8% of energy from renewable sources

The London Array The London Array will be around 15km from the Kent and Essex coasts in the outer Thames Estuary.
London Array could have over 340 turbines The London Array could have over 340 turbines in an area of up to around 245km².
Proposed onshore substation Layout of the proposed onshore substation at Cleve Hill.
World's Largest Offshore Wind Farm The 1,000MW London Array will be the world's largest offshore wind farm.
The London Array The London Array could cost around £1.5bn.